4.1 Switchover Approval Meetings with Functional Units
4.2 Power Check for Racks
4.3 Installation of Test Servers
4.4 Primary Systems Check
Execution Phase
5.1 Network Shutdown and Move
Description In order to outline what work breakdown structure (WBS) presented in the case, I went through all the details about the project and tasks mentioned in the scenario and carefully took a look at them. In doing so, I created a list of project phases and then divided them into smaller tasks each. All the tasks of every phase were grouped clearly by phase to demonstrate an unbiased view of the project's overall scope and schedule. WBS develops a detailed and complete work schedule of the project's timeline and the expected outcome, which in turn allows the project manager to plan his/her activities.
Risk Register for Future Technology Data Center Relocation Project:
Contractor Delays
Likelihood: Medium
Impact: High
Mitigation: Regular communication and monitoring of contractor progress.