Assignment II

docx

School

Stevens Institute Of Technology *

*We aren’t endorsed by this school

Course

612

Subject

Industrial Engineering

Date

Dec 6, 2023

Type

docx

Pages

6

Uploaded by AdmiralLionMaster307

Report
Caitlin Carroll EM 612 – Project Management of Complex Systems Assignment II – Shea Stadium Renovation Project Summary Start date: 1/14/2004 Estimated End Date: March 22, 2005 Estimated Duration: 62 Weeks Contract Value: $350,000,000 Estimated Profit: $20,000,000
Risk Analysis Risk 1 – NYC Labor Strike : On Saturday, October 30, 2004, the NYC Labor Agreements come to an end. This could cause the risk of a strike beginning on the next workday, Monday, November 1, 2004. The strike could last four weeks. Assuming all of this, work would resume on Monday, November 29, 2004. During this time, the sod installation and erection of facades and boxes would be delayed. This delay impacts the critical task, façade and box completion which affects the date the project will end. In the event of a strike the project will have a new end date of April 19, 2005, four weeks after March 22, 2005. This risk ruins the plan to finish the project 7 business days ahead of schedule and adds an extra 19 days of delay. 7 DaysEarly × $ 100,000 Day Early + 19 DaysLate × $ 250,000 Day Late =− $ 5,450,000 A four-week labor strike in November will cost the project $5,450,000. Risk Rating: Very High Consequence: -$5,450,000 Probability of Occurrence: 50% Expected Value: -$2,725,000 Updated WBS and Gnatt Chart, Risk 1
Risk 2 – Inclement Weather: May of 2003 was abnormally cold and wet. If May of 2004 is equally cold and wet, the stadium renovation will be delayed. Fortunately, the playing field tasks are not part of the critical path. Since the delay only affects work done on the playing field, the estimated project end date will not be affected. The inclement weather would push back the playing field excavation until May 18 th , 2004, two weeks later than estimated. This causes the full playing field renovation to be delayed until November 18, 2004. The end date will not be changed, but it will cause a planning issue for the construction of the playing field, especially if the Mets desire to use the field before the rest of the stadium is complete. Risk Rating: Low Consequence: Playing Field Construction +4.4 Weeks Updated WBS and Gnatt Chart, Risk 2
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Risk Matrix Shea Stadium Renovation – Ace Builders Project Evaluation Summary BCWS: $350,000,000 ACWP: $166,327,000 BCWP: $170,152,750 [+$3,825,750 from ACWP] Schedule The Shea Stadium renovation is behind schedule as of December 10, 2004. Erection of façade and boxes, painting, dressing Rooms/offices, roof prefabrication, scoreboard, lights, and wiring/HVAC are all delayed. Luckily, the roof erection, the new seats, and exterior infrastructure have begun ahead of schedule. Project SPI: 0.6032 – The project is behind schedule, significantly. SV: The project should have earned an additional $111,942,250.00 in value by this point. Cost Project CPI: 1.023 – The project is under budget. CV: The project was expected to have spent an additional $3,825,00.00 by the point at which it had earned as much value as it has. Completion EAC: $342,132,069.57 – The project is estimated to complete under budget. Completion Date: The project is set to end on May 25, 2005. This exceeds the 15-month project life constraint, therefore the work on the stadium must be expedited. Some of the money saved could be allocated to more labor for the remaining construction to help resolve this issue.
Updated WBS and Gnatt Chart, %Completion Quantitative Project Evaluation, Excel
Note: Inconsistency with project completion percentage. 63% was accurate before relevelling the project. 42% was calculated after levelling. This did not affect the analysis.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help