ETI4448 Assignment 4
docx
keyboard_arrow_up
School
Daytona State College *
*We aren’t endorsed by this school
Course
ETI 4448
Subject
Industrial Engineering
Date
Dec 6, 2023
Type
docx
Pages
2
Uploaded by SuperHumanOxide10248
Engineering Technology Department
Project Management and Senior Design I
ETI 4448
Assignment 4
Your company did a proposal for a client to develop a software application to satisfy
some of the client’s functional needs. The project scope was defined and was approved by
the customer. The project manager now in the phase of planning for the project activities.
Help the project manager to develop the plan using MS Project software package using
the following information:
1.
The project activities have been identified as follows:
Phase 1:
1.
Feasibility Study
Phase 2:
1.
Preliminary analysis
2.
Detailed analysis
3.
Hire Staff
Phase 3:
1.
Design software
2.
Purchase hardware
3.
Training staff
4.
Coding
Phase 4:
1.
Final Testing
2.
Implementation
2.
Estimating the duration through three-point techniques the project manager got
the following:
Feasibility Study will take 6 days
Preliminary analysis will take 2 weeks and we cannot start analysis until
we are done with the feasibility study
Detailed analysis will take 3 weeks and we cannot start analysis until we
are done with the preliminary analysis
Hire Staff will take 7 days and we cannot start hiring until we are done
with the preliminary analysis
Design software will take 8 days and we cannot start designing until we
are done with the detailed analysis
Purchase hardware will take 2 days and we cannot purchase hardware
until we are done with hiring the needed staff
Training staff will take 4 days and we cannot start training until we are
done with hiring the needed staff
Coding will take 4 weeks and we cannot start coding until we are done
with designing the software
Final Testing will take 3 days and we cannot start testing until we are done
with training the staff and done with the coding
Implementation will take 1 week, and we cannot start the implementation
until we are done with the final testing
Assuming you have the following employees:
o
1 Researcher $50 per hour
o
2 Programmer Analysts $60 per hour
o
2 Administrative assistants $40 per hour
o
1 Software Designer $50 per hour
o
1 Programmer $70 per hour
o
1 Testing Engineer $45 per hour
o
2 Software Engin4eers $60 per hour
1.
Assign employees to activities based on their title
2.
Calculate the total cost for the project staff assuming that they will
work for 40 hours per week, no holidays, no vacations, and no
overtime. Develop the plan using MS Project, add project
employees including their wages, find the total cost, and submit
your assignment in MS Project file format that includes all
requirements.