Date:
January 25, 2024
To:
The University of Arizona
From:
Alana Lipp, Project Manager – alanalipp@arizona.edu
757-239-7027
Abigail Knight, Monitor – abigailknight@arizona.edu
985-516-8331
Eden Glucksman, Designer – egparrie@gmail.com
818-207-3584
Sandra Olguin, Researcher – solguin@arizona.edu
863-244-3037
Subject:
Team Charter and Task Schedule
Table of Contents: I.Problem
II. Methods
a)
Communication Methods
b)
Meeting Frequency/ Schedule
c)
Technologies Used
d)
Collaborative Tools Used
III. Research Guidelines
a)
Team Accountability Logistics
b)
Team Goals
c)
Expectations for Accomplishing Tasks
d)
Scheduling Conflicts Interfering with this Project
e)
Team Members Strengths, Weaknesses, & Goals
IV. Schedule
I. Problem
Scheduling meetings and collaboration can be challenging due to varying time zones but after comparing schedules we came to a set date and time to have regular meetings. Unequal access to technology or internet connectivity problems may hinder our progress but we plan to record each of our meetings so that if one of us fails to make contact we will all be kept up to date. Coordinating tasks and ensuring everyone is on the same page can be difficult with dispersed team members but with our team group chat we keep up with each other regularly. Differing cultural norms and communication styles may impact team dynamics and decision-making processes but it makes for a more in depth report that will reach a broader audience. It's harder
to monitor and address imbalances in workload when team members are physically distant. Building a cohesive team spirit is more challenging without regular in-person interactions so we try to stay in touch as often as our schedules allow us
.
II. Methods
a. Communication Methods
Our team has opted for Facetime and text messaging as our primary means of communication. We’ve established a group chat as our central hub for all communication, providing a straightforward and streamlined method. Additionally, Facetime enables us to conduct face-to-
face discussions, fostering a more personal and collaborative approach to project-related conversations. b. Meeting Frequency and Schedule
Our team has established a weekly meeting convening on Facetime every Saturday at 12:00pm MST. In the meantime, we maintain constant communication through text messages, ensuring that information flows seamlessly. If the need arises for additional meetings, we have the flexibility to coordinate and schedule them efficiently through our group chat. This approach enhances our overall collaboration and ensures effective communication within the team. c. Technologies Used
Our team will be using reliable sources from library databases when gathering research for the report. When creating the report we will utilize Adobe photoshop, Microsoft Word, etc. These resources will help ensure that our report is accurate, thoroughly researched, and enhances its overall quality and credibility. d. Collaborative Tools Used
Our team has opted for Google Docs as our central collaborative writing tool, providing a seamless platform for joint project development. Utilizing a shared Google Drive folder enhances our collaboration, allowing team members to contribute and access project materials effortlessly. In addition to our collaborative workspace, we maintain an active group chat for real-time communication and hold weekly team meetings to discuss progress, address any challenges, and ensure everyone is aligned on project goals. This comprehensive approach ensures effective communication and enhances the overall collaborative experience within our team. III. Research Guidelines
a. Team Accountability Logistics
Accountability within a team is important in order to be successful. Team accountability is the
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
H.W(11):- The table below shows the duration and direct costs for the activities of
a construction project. It is required to calculate the duration of the project that
achieves the lowest possible total cost using the technique of crashing if the
indirect costs are 5000$ per week.
Activity
Normal Time
Normał Cost
Crash Time
Crash Cost
(NT) Weeks
3
(NC) $
6000
CC) $
12000
(CT) Weeks
A
5
3000
3
5000
4000
6000
3
2000
6.
3000
3
6.
9000
24000
Total Direct
23000
Cost
arrow_forward
Instructions
ASSIGNMENT
PROJECT SCENARIO: You are married and you are the
father or mother of a family of five with kids ages 10, 13 and
15) and a dog. The family has decided to take a camping trip
when the children are out of school for the summer. The
planned family camping trip is the project you will use to complete this assignment.
INSTRUCTIONS: Create a Responsibility Matrix for no less than seven activities to
be addressed in preparation for the family camping trip. Every member of the family
must be assigned primary responsibility to complete at least or more activities for the
project. Also, decide whether the dog will go on the camping trip with the family or
whether arrangements will be made for someone to care for the dog while the family
is away. Based on your decision regarding the dog, you must include at least one
activity associated with the dog as part of the project responsibility matrix.
Within the matrix, use "R" to indicate which individual has primary…
arrow_forward
EX6-11 (Algo) A large Southeast city is requesting federal...
A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a
network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet
this requirement. She has gathered the activity time estimates and their dependencies shown here.
10 Description
A
B
Survey
Soils report
C Traffic design
0
Lot layout.
Approve design
E
F 111umination
G Drainage
H Landscape
I
Signage
3 Bid proposal
The project is expected to take
The critical path is
Early start for Activity E is:
Late finish for Activity F is:
Slack for Activity Cis:
Predecessor
None
A
A
A
B, C, D.
E
E
E
t
F. G, H, 1
Time
(days)
11
18.
15
7
85
25
18
23
15
8
days.
day(s)
arrow_forward
Paragraph
Styles
Eg
Problem 2
The table below contains data for the installation of new equipment in a manufacturing process for
a steel corporation. Your company is responsible for the installation project. Indirect costs are
$6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for
every week the project is delayed beyond week 15.
Immediate
Normal Time
Crash Time
Normal Cost
Crash Cost
Activity
Predecessor(s)
(weeks)
(weeks)
($)
7,000
3,000
($)
A
None
1
10,000
None
2
3,000
A
3
1
12,000
40,000
12,000
28,000
E
C
1
1
8,000
8,000
F
D, E
5
5,000
15,000
3
9,000
18,000
F, G
6.
14,000
32,000
Construct a network diagram for the project.
a.
b. What are the project completion time and the total cost under normal conditions?
What is the shortest time duration for this project regardless of cost? What is the resulting total cost?
с.
d. What is the minimal total cost associated with completing the project in 16 weeks?
e.
What is the total time for the…
arrow_forward
What is the scope of the following project? (2 paragraphs please)
Barbados GIS – The United Nations Food and Agriculture Organization (FAO) has collaborated with the Ministry of Maritime Affairs and the Blue Economy, and local business Adams Aquafarms, on a project to train persons in aquaponics. Aquaponics is a sustainable way of integrating land-based fish farming with plant production. Both are placed in a tank, and the set up allows for them to coexist, with the waste produced by the fish fertilizing the plants, while the plants purify the water for the fish. The training, funded by the FAO, will take place at a demonstration facility, located at Adams Aquafarms, Hopewell, St. Thomas. The FAO is currently targeting 30 entrepreneurs and 10 teachers. Minister of Maritime Affairs and the Blue Economy, Kirk Humphrey, believes the project will be “transformative”, as it has the potential to empower Barbadians. “In aquaponics, you have the opportunity to have, at the same time,…
arrow_forward
Which alternative would you choose if you were in Jane's position?
arrow_forward
How can this situation be prevented from occurring again?
arrow_forward
Good day may I have some help with part D and E in the attached pic
arrow_forward
project operation management
please answer
arrow_forward
Subpart 2. What could Brenda done to avoid this incident?
arrow_forward
Students shall, with a point of view of him/herself as project manager (PM), submit a Project Management Plan (PMP) for the given engineering project below: - “Procurement & Installation of Emergency Generator at Fire station” Students are allowed to propose their own project, given that the projects shall have enough scale to address the element described below:- a. Student should produce a project definition statement regarding the proposed project. b. Student should propose a suitable project team to carry out the project. Student should in the PMP describe the duties and power of different team memebrs in the project. c. The PMP shall include a risk management plan, which student shall identify, analyse and proposed mitigations measures for smooth delivery of the project deliverables. The risk manamgenet plan shall include a risk register d. The PMP shall include a quality management plan, which student shall propose a method statement to control the quality of the delivery of…
arrow_forward
Case Study
The CEO of your company needs to employ a personal assistant for helping him to manage his schedules and in
meetings. The CEO needs an office Assistant to oranize various files and document n his office. The assistant will be responsible to book tickets for the CEO for his business rips home and abroad. The assistant will be required to wrie e-mails on behalf o the CEO. Moreover, he or she will be responsible for wrtng meeting minutes. You are the Manager of HR. The CEO wants you to post a vacancy announce on newspaper to find a suitable Personal Assistant/ Ofice Assistant. The CEO wants to hire someone wih exclient command over writing and
spoken English, good speed in typing, two years of work exprience in similar position. The ideal candidate should not be over 25 years old. You will conduct job analysis for the post of personal assistant and publish a
vacancy announcement on local newspaper.
a)What will be the elements of Job description in the vacancy announcement?…
arrow_forward
EX6-12 (Algo) You are creating a customer database...
You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below,
complete the forward and backward pass, compute activity slack, and identify the critical path.
How long will this project take?
ABCDACHSX
K
L
Description
Systems
Subsystem A design
Subsystem B design
Subsystem C design
Program A
Program B
Program C
Subsystem A test
Subsystem B test
Subsystem C test
Integration
Integration test
days.
Predecessor
None
A
A
A
B
с
D
E
F
G
H, I, J
K
Time
(days)
7
3
1
3
5
15
5
3
3
5
3
arrow_forward
Part 1: The 5 project management groups have wide industry application in modern day project management. By using practical examples of your choice, demonstrate the practical application of the project management processes in bringing a project to a successful end (Detailed response required, also acknowledge information sources).
Part 2: A gantt chart is widely applied in project management as a project scheduling tool,whose format is in bar chart form. Critically examine a gantt chart as a project scheduling tool and practically demonstrate how it can also be used as a project planning and control technique (Detailed response required, also acknowledge information sources).
arrow_forward
Topic: Globla Health
GrenCHAP was founded in 2001 with a primary focus on Men who have Sex with Men (MSM), in response to the regional partnership between The Global Fund and PANCAP.
The Global Fund is a unique global public/private partnership dedicated to attracting and disbursing additional resources to prevent and treat HIV/AIDS, Tuberculosis and Malaria. It is active in the Caribbean and provides major funding to the Pan Caribbean Partnership Against HIV/AIDS (PANCAP) for the region’s response to HIV/AIDS.
Today, GrenCHAP Inc. is a non-governmental organisation working to promote Sexual Reproductive Health and Human Rights, with a focus on marginalised populations, such as LGBT and Sex Workers.
Over the years, our workplan has received financial support from the U.S. President’s Emergency Plan for AIDS Relief (PEPFAR), the Caribbean HIV/AIDS Alliance, amfAR, and, at present the Open Society Foundations (OSF).
Question: What are the major forces of their work ?
arrow_forward
What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days?
NORMAL
CRASH
TIME (DAYS) TIME (DAYS)
NORMAL
COST
8
6
6
4
ACTIVITY
Design (A)
Wiring (B)
Chip install (C)
Software (D)
Testing (E)
8
5335
400
1,000
600
1,000
1,100
CRASH
COST
450
1,100
700
1,300
1,625
IMMEDIATE PREDECESSOR(S)
A, B
C
The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $900 (enter your response as a
whole number).
arrow_forward
None
arrow_forward
Only typed explanation
The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 14.
What is the shortest time duration for this project regardless of cost?
What is the minimum total cost associated with completing the project in 14 weeks?
What is the total time of the minimum-cost schedule?
arrow_forward
3. General Construction Company
General Construction Company has a contract to build three lower‐income apartment buildings for the city of Santa Fe, New Mexico. During the construction of the first building, the Project Manager formed an auditing team to audit the construction process for each building. He asked the team to develop a list of minimum requirements for the projects and use this as a baseline in the audit. While reviewing the contract documents, one of the audit team members found a discrepancy between the contract minimum requirements and the City’s minimum requirements. Based on his findings, he has told the project manager that he has decided to contact the city administrator and discuss the problem. Question: If you were the project manager, how would you handle this situation? How can a customer be assured of satisfactory project completion?
arrow_forward
9:01 PM
9יוה וi"
Group Work.pdf
UNIVERSITY OF PROFESSIONAL STUDIES, ACCRA (UPSA)
主
DIPLOMA PROGRAMME
LEVEL 100
PDBA 117: BUSINESS COMMUNICATION
2021 ACADEMIC YEAR, FIRST SEMESTER
GROUP WORK
QUESTION
You are the Managing Director of MediConsult, a medical supplies company, located at Tema.
Due to the COVID-19 pandemic, your regular import of supplies has been cut by half. As a result,
you are unable to meet the demands of most of your clients. Write a letter to the Procurement
Director of Abala Hospital, Spintex Road, to inform her of your inability to supply her company's
request for face masks.
INSTRUCTIONS
1. All letters should come on a letter head
2. Use a standard business letter format
3. Use a fully-blocked layout
4. Final submissions should be in a pdf format.
5. Submissions should be via UPSA Virtual only
6. Clearly state the following on the cover page:
a. your class (Example: Public Relations Group 1)
b. your group (Example: Group 10)
c. names and index numbers of all group…
arrow_forward
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?
Normal
Cost
$800
$200
$600
$750
$1,200
Normal
Crash
Activity Time (days) Time (days)
4
3
8
6
The total cost of crashing the project by 4 days is $
ABCDE
487
355
(Enter your response as a whole number.)
Total Cost
with Crashing Immediate Predecessor(s)
$1,500
$1,650
By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)
Each Activity Should be
Reduced BY
(days)
Activity
A
B
C
D
E
$1,100
$600
$650
A
C
arrow_forward
What action should Jane take?
arrow_forward
how do i find the slack?
Note:-
Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
Answer completely.
You will get up vote for sure.
arrow_forward
4,
arrow_forward
what does each employee have a right to expect in terms of equitable treatment with regard to pay and commission opportunities?
arrow_forward
MODELLING AND SIMULATION
1. What is the best way to plan a simulation project? Why?
2. Does project management help you to simulate a model? In what way/s?
3. Car dealers have realized how profitable it can be to sell automobiles by using the Web. Pretend that you work for a local car dealership that is part of a large chain of car industry. Create a project management process (include the sub-processes) that you will implement in developing such web-based system.
arrow_forward
1. A project has been defined to contain the following list of activities along with their required times for completion.
What would happen if activity 6 were revised to take 6 weeks instead of 1 week?
2. Construct a Gantt chart for the project defined in Problem 1.
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Related Questions
- H.W(11):- The table below shows the duration and direct costs for the activities of a construction project. It is required to calculate the duration of the project that achieves the lowest possible total cost using the technique of crashing if the indirect costs are 5000$ per week. Activity Normal Time Normał Cost Crash Time Crash Cost (NT) Weeks 3 (NC) $ 6000 CC) $ 12000 (CT) Weeks A 5 3000 3 5000 4000 6000 3 2000 6. 3000 3 6. 9000 24000 Total Direct 23000 Costarrow_forwardInstructions ASSIGNMENT PROJECT SCENARIO: You are married and you are the father or mother of a family of five with kids ages 10, 13 and 15) and a dog. The family has decided to take a camping trip when the children are out of school for the summer. The planned family camping trip is the project you will use to complete this assignment. INSTRUCTIONS: Create a Responsibility Matrix for no less than seven activities to be addressed in preparation for the family camping trip. Every member of the family must be assigned primary responsibility to complete at least or more activities for the project. Also, decide whether the dog will go on the camping trip with the family or whether arrangements will be made for someone to care for the dog while the family is away. Based on your decision regarding the dog, you must include at least one activity associated with the dog as part of the project responsibility matrix. Within the matrix, use "R" to indicate which individual has primary…arrow_forwardEX6-11 (Algo) A large Southeast city is requesting federal... A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. 10 Description A B Survey Soils report C Traffic design 0 Lot layout. Approve design E F 111umination G Drainage H Landscape I Signage 3 Bid proposal The project is expected to take The critical path is Early start for Activity E is: Late finish for Activity F is: Slack for Activity Cis: Predecessor None A A A B, C, D. E E E t F. G, H, 1 Time (days) 11 18. 15 7 85 25 18 23 15 8 days. day(s)arrow_forward
- Paragraph Styles Eg Problem 2 The table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Immediate Normal Time Crash Time Normal Cost Crash Cost Activity Predecessor(s) (weeks) (weeks) ($) 7,000 3,000 ($) A None 1 10,000 None 2 3,000 A 3 1 12,000 40,000 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 5,000 15,000 3 9,000 18,000 F, G 6. 14,000 32,000 Construct a network diagram for the project. a. b. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? с. d. What is the minimal total cost associated with completing the project in 16 weeks? e. What is the total time for the…arrow_forwardWhat is the scope of the following project? (2 paragraphs please) Barbados GIS – The United Nations Food and Agriculture Organization (FAO) has collaborated with the Ministry of Maritime Affairs and the Blue Economy, and local business Adams Aquafarms, on a project to train persons in aquaponics. Aquaponics is a sustainable way of integrating land-based fish farming with plant production. Both are placed in a tank, and the set up allows for them to coexist, with the waste produced by the fish fertilizing the plants, while the plants purify the water for the fish. The training, funded by the FAO, will take place at a demonstration facility, located at Adams Aquafarms, Hopewell, St. Thomas. The FAO is currently targeting 30 entrepreneurs and 10 teachers. Minister of Maritime Affairs and the Blue Economy, Kirk Humphrey, believes the project will be “transformative”, as it has the potential to empower Barbadians. “In aquaponics, you have the opportunity to have, at the same time,…arrow_forwardWhich alternative would you choose if you were in Jane's position?arrow_forward
- Subpart 2. What could Brenda done to avoid this incident?arrow_forwardStudents shall, with a point of view of him/herself as project manager (PM), submit a Project Management Plan (PMP) for the given engineering project below: - “Procurement & Installation of Emergency Generator at Fire station” Students are allowed to propose their own project, given that the projects shall have enough scale to address the element described below:- a. Student should produce a project definition statement regarding the proposed project. b. Student should propose a suitable project team to carry out the project. Student should in the PMP describe the duties and power of different team memebrs in the project. c. The PMP shall include a risk management plan, which student shall identify, analyse and proposed mitigations measures for smooth delivery of the project deliverables. The risk manamgenet plan shall include a risk register d. The PMP shall include a quality management plan, which student shall propose a method statement to control the quality of the delivery of…arrow_forwardCase Study The CEO of your company needs to employ a personal assistant for helping him to manage his schedules and in meetings. The CEO needs an office Assistant to oranize various files and document n his office. The assistant will be responsible to book tickets for the CEO for his business rips home and abroad. The assistant will be required to wrie e-mails on behalf o the CEO. Moreover, he or she will be responsible for wrtng meeting minutes. You are the Manager of HR. The CEO wants you to post a vacancy announce on newspaper to find a suitable Personal Assistant/ Ofice Assistant. The CEO wants to hire someone wih exclient command over writing and spoken English, good speed in typing, two years of work exprience in similar position. The ideal candidate should not be over 25 years old. You will conduct job analysis for the post of personal assistant and publish a vacancy announcement on local newspaper. a)What will be the elements of Job description in the vacancy announcement?…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON