1 TEXAS A&M UNIVERSITY-KINGSVILLE Frank H. Dotterweich College of Engineering Department of Mechanical and Industrial Engineering Engineering Project Management Exam No. 3 Name:Garza, Adriana. Date: 11/30/23 Last First K#: 00447969 Important: To get the full credits, show all your works and write as detail as you can, otherwise you will get a partial credit. 1. Consider a project with the following information, and answer the questions, 1. a) - 1. d). Activity Duration (days) Predecessor Resource Hours Needed per day A 2 None 6 B 3 A 6 C 6 B 5 D 5 A 3 E 3 C, D 7 1. a) Draw a network diagram.
2 1. b) Find ES, EF, LS, LF and Slack and complete the following table. Path: Durtion: A-B-C-E- 14 A-B-D-E 13 A-B-C-D 16 The longest is A-B-C-D ActivityDuration (days) Predecessor ES EF LS LF Slack A 2 - 0 2 0 2 0 B 3 A 2 6 2 6 0 C 6 B 2 10 5 13 3 D 5 A 13 8 3 9 1 E 3 C, D 6 13 6 13 0
1. cc) Complete the following Time-Phased Resource Loading Table for this project. Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 A 2 B 4 C 8 D 6 E 7 Total 1. d) Assume that the maximum resource hours per day available for the project are eight. Level the resource loading table below without project delay. Assume that hours for each task cannot be separated or divided. Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 A B C D E Total 2. There is a project that starts on August, and expects to finish at the end of December with