DETAILED COST ESTIMATE FOR THE CONSTRUCTION OF TWO-STOREY RESIDENTIAL BUILDING WITH ROOF DECK

Location: Naga City
Owner: Ryan M. Bajaro

A. SITEWORKS

Item Description | Quantity | Unit | Unit Cost (Pesos) | Total Cost | 1. Clearing and Grubbing | 630 | m2 | 50 | 31,500 | 2. Excavation | 140 | m3 | 500 | 70,000 | 3. Gravel Bedding | 30 | m3 | 850 | 25,500 | 4. Madrigal Soil (Fill) | 49 | m3 | 350 | 17,150 | 5. Labor Cost (30%) | --- | --- | --- | 43,245 | 6. Indirect Cost (10%) | --- | --- | --- | 14,415 | Total: 201,810
…show more content…
Panel Door | 11 | Set | varies | 77,000 | 2. PVC Door | 6 | Set | 3500 | 21,000 | 3. Steel Door | 1 | Set | 4000 | 4,000 | 4. Indirect Cost (10%) | --- | --- | --- | 10,200 | Total: 112,200 Pesos |

H. PAINTING

Item Description | Quantity | Unit | Unit Cost (Pesos) | Total Cost | 1. Flatwall Enamel Paint QDE | 54 | gal | 500 | 27,000 | 2. Semi-Gloss Paint QDE | 45 | gal | 530 | 23,850 | 3. Paint Thinner | 31 | gal | 300 | 9,300 | 4. 4” Paint Brush | 16 | Pcs | 60 | 960 | 5. 2” Paint Brush | 15 | Pcs | 25 | 375 | 6. Automotive Lacquer Putty | 7 | gal | 580 | 4,060 | 7. Lacquer Thinner | 7 | gal | 250 | 1,750 | 8. Sanding Paper #120 | 384 | pcs | 20 | 7,680 | 9. Concrete Neutralizer | 23 | gal | 380 | 8,740 | 10. Flatwall Latex | 31 | tcan | 1,980 | 61,380 | 11. Semi-Gloss Latex | 16 | tcan | 2,000 | 32,000 | 12. Acri-Color Paints | --- | L.S. | 500 | 500 | 13. Labor Cost (30%) | --- | --- | --- | 53,279 | 14. Indirect Cost (10%) | --- | --- | --- | 17,760 | Total: 248,634 Pesos |

I. FORMS AND SCAFFOLDING

Item Description | Quantity | Unit | Unit Cost