Chapter 9 Homework

1353 Words Jul 5th, 2012 6 Pages
Chapter 9

reducing project duration

Review Questions

1. What are five common reasons for crashing a project?

Reasons given could include:

• Imposed deadline in which disfavor will be earned by not meeting superior’s deadline • Time to market competitive advantage • Realize benefits from incentive contracts • To make up for lost time and avoid contract penalties • Save extensive overhead costs • Free up resources to work on other projects • Exceed customer expectations.

2. What are the advantages and disadvantages of reducing project scope to accelerate a project? What can be done to reduce the disadvantages?

Reducing the scope of the project can lead to big savings both in time and costs. It
…show more content…
Which activity would you shorten to reduce the project duration by 2 weeks? Why?

[pic]

3. Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost?

[pic]

[pic]

[pic]

4. If the indirect costs for each duration are $1,200 for 16 weeks, $1,130 for 15 weeks, $1,000 for 14 weeks, $900 for 13 weeks,