Cmit 495 Implementation Plan Essay

13676 Words May 10th, 2016 55 Pages
World-Wide Trading Company: Project Implementation Plan
Group 3
Kristine Bird (AD Forest Domain OU, Groups and GPO Implementation)
Ryan Bonisch (Contact list and LAN Implementation Tasks)
Anthony Campo (Configuration of Routers, Switches, and VLANs)
Gerald Casanada (Voice VLAN, Wireless, DHCP and DNS)
Jennifer Coleman (AD Implementation and Tasks lists for AD Policies)
Billie Jo Derouin (Security Implementation)
Raymond Mack (Security Technology and Timeline)
University of Maryland University College
CMIT 495
Professor Sam Musa
February 28, 2016





Table of Contents
Introduction 2
Purpose 3
Implementation Requirements 3
Project Contact List 3
Tool List 3
Equipment Installation Plan 5
Project
…show more content…
Table 2













Region/Users | Location | Details |
VP NW, SW, NE, SE , Staff, Brokers, Conf Room 1 | Quadrant one, Floor 1, Rack # 1 Room 104 | All access switches and associated equipment will be installed in this quadrant. |
President, Executives Asst, Staff, Brokers, Reception | Quadrant two, Floor 1, Rack#2 Room 105 | All access switches and associated equipment will be installed in this quadrant. |
VP OPR, CEO (IT,FIN, HR), Staff, Brokers | Quadrant three, Floor 1, Rack#3, Room 106 | All access switches and associated equipment will be installed in this quadrant. |
Conf Room 2, Staff, Reception, Brokers | Quadrant four, Floor 1, Rack#4, Room 107 | All access switches and associated equipment will be installed in this quadrant. |
Classified Users and Equipment | Quadrant two Classified Server Room, Floor 1, Rack#5 Room 108 | All classified equipment and access |
Equipment Installation Plan

The WWTC equipment installation will be divided into four quadrants in accordance with the floor below floor plan.
Project TimeLine





Lan Implementation task

Step | Task |
1. | Utilize Proper Electrostatic Discharge Preventative Measures |
2. | Validate Area is Prepared for Installation |
3. | Install Server Rack…