preview

Designing A Engineer 's Field Office

Decent Essays

The project’s critical path begins with MassDOT issues Notice to Proceed to the Contractor and then, the Contractor will locate and establish the Engineer 's Field Office, Mobilize to the project site, install Project and Construction Signage, perform Sedimentation and Erosion Controls, Stake Pre-Stage Pole Locations, Prepare Site for Pre-Stage 1 Utility Relocation, Clearing and Grubbing, perform Tree Trimming and Protection, install Temporary Fencing, Test Pit at Boring BB-4 for Obstructions, Construct Wheel Chair Ramps 3 and 4, Detour Pedestrian Traffic off West Sidewalk and Setup West Work Zone #1. Once the Project Startup work is complete, the Contractor will start the Utility Bridge work by the Support of Excavation for the Northwest Abutment, the Demolition of the Canal Wall of the Northwest Abutment, the Excavation of the Northwest Abutment, and the Construct of the Northwest Abutment Foundation. The Contractor will repeat the same steps above to construct the Southwest Abutment Foundation. Finally the Contractor will install the Utility Bridge. Once the Utility Bridge work is complete, the Contractor will start the Utility Relocation work by Installing Electrical Manholes, Installing Duct Banks, and Installing Electrical Riser at Utility Pole. Once this work is completed, the Contractor will achieve Milestone MS#05 - Interim MS - NEI Completes Work Required to Allow for Bridge Supported Utility Connections. After the Contractor completion of Milestone MS#05,

Get Access