SCHOOL OF ENGINEERING AND BUILT ENVIRONMENT
COURSEWORK COVER SHEET
FOR THE ATTENTION OF LECTURER: Dr. Michael Tong
(PLEASE PRINT)
Student Name: Ngozi Sam-moseli
Matriculation Number:S1421753 Year of Study: 2014-15
Programme Title: International Project Management (Oil & Gas)
Assignment Title: Project Planning (PM coursework 2)
Module: Project Management (MMN221207-14-B)
Student Declaration
This piece of work is not plagiarised. It is my original work and has not been submitted elsewhere in fulfilment of the requirements of this or any other award.
Signature: Date: 29th April, 2015
Your mark could have been higher if:
Additional Marker Comments:
Marker Signature: Total Mark
Marker Name: Dr. Michael Tong
Date:
Table of content
Table of Contents
Table of content 1
1.0 INTRODUCTION 2
2.0 PROJECT MANAGEMENT CONCEPT 3
2.1 What is a Project? 3
2.2 Project Management (PM) 3
3.0 PROJECT PLANNING 4
4.0 PROJECT MANAGEMENT MONITORING AND CONTROLLING TECHNIQUES. 5
4.1 Tools and techniques for Project plan monitoring 6
4.2 Tools & techniques for Project cost/budget monitoring and control 10
4.3 Monitoring by Project Team 11
5.0 RESOLUTION OF DELAYS TO CRITICAL PATH ACTIVITIES. 11
6.0 RECOMMENDATION AS TO HOW TO MAXIMISE LEARNING WITHIN AND BETWEEN PROJECTS 12
REFERENCES 13
1.0 INTRODUCTION
The construction industry needs tools and techniques for land use, economic development, and environment planning to cope with development in various locations. This
During the construction phase, there will be a lot happening all over. This may vary from the actual erecting of the building, to the transport of goods, to the extraction of materials needed, etc. There will be a lot of damage done to the o-zone layer, a lot of habitat and biodiversity destroyed, amongst other things.
‘I confirm that this piece of work which I have submitted is all my own work and that all references and quotations from both primary and secondary sources have been fully identified and properly acknowledged in footnotes and bibliography.’
Modern methods of construction (MMC) are needed in the industry because of a growing number of factorts that are effecting our built environment and the
I certify that the writing in this assignment is my individual work and is my sole intellectual property. It does not contain the ideas or writing of other individuals/authors.
Over the past few years, the construction industry has been changing dramatically. One of the most important stages in the construction management and business management is the planning phase. They share similar two main levels of planning which are the strategic and operational planning. However, business management planning to decide in advance what should be done, and how to do it, when you do and you are done. On the other hand, Construction management strategic planning is to deal with selection on a high level of overall objective of the project, including the scope, procurement methods, schedules and financing options but the planning of operations, including the
“This is to certify that the work I am submitting is my own. All external references and sources are clearly acknowledged and identified within the contents. I am aware of the University of Warwick regulation concerning plagiarism and collusion.
□ I have read and understood the avoiding plagiarism guidelines at http://www.swinburne.edu.au/ltas/plagiarism/students.htm and no part of this work has been copied or paraphrased from any other source except where this has been clearly acknowledged in the body of the assignment and included in the reference list.
By submitting this assignment, I declare that I have retained a suitable copy of this assignment, have not previously submitted this work for assessment and have ensured that it complies with university and school regulations, especially concerning plagiarism and copyright.
This is to certify that the following essay is my own work and that I have not
I declare that this submission is my own work with respect to plagiarism and does not violate any copyright laws.
I confirm that I have read the University regulations on plagiarism, and that this assignment is my own work.
hereby declare that this is my own work and that all non-original information is appropriately acknowledged. No part of this assessment has been written/created for me by any other person. I am aware of the consequences of plagiarism and will abide by the Plagiarism policy in this regard. I have retained a copy of this assessment.
By submitting this work, I am declaring that I am the originator of this work and that all other original sources used in this work have been appropriately acknowledged. I understand that plagiarism is the act of taking and using the whole or any part of another person’s work and presenting it as my own without proper acknowledgement. I also understand that plagiarism is an academic offence and that disciplinary action will be taken for plagiarism.
The number of personnel on the project had increased to over five hundred people. Furniture consultant, Jasper Morrison was appointed for public areas. In February, The Arts Council of England Lottery Fund awarded £6.2 million grant to allow additional display area in order to be built in time for the opening. As this was the largest project at the time, the Tate project had brought to the cost equivalent to £134.2 million. The orginal hand-over date was announced to be in March. Mid-year of 1999, glass panes were installed and Turbine Hall bridge stair was also installed.
Declaration: I hereby declare that the submitted TMA is my own work and I have not copied any other person’s work or plagiarized in any other form as specified above.