Mrp Problems

864 Words Nov 29th, 2014 4 Pages
10.In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead-time is one week.

Item: JOH: 40LT: 1SS: 0Q: L4L | | Week Number | | Item J | 0 | 1 | 2 | 3 | 4 | 5 | | Gross requirements | | | 75 | | 50 | 70 | | Scheduled receipts | | | | | | | | On Hand | 40 | 40 | 0 | 0 | 0 | | | Net requirements | 0 | 35 | | 50 | 70 | | | Planned order receipts | | 35 | | 50 | 70 | | | Planned order releases | 35 | | 50 | 70 | | |

11. Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E.
…show more content…
| | | | | 100 | | | | | Planned order releases | | | | | | | 100 | | | | Item: | B | Gross requirements | | | | | | | | 200 | | | OH: | 0 | Scheduled receipts | | | | | | | | | | | LT: | 1 | Projected available balance | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | SS: | 0 | Net requirements | | | | | | | | 200 | | | Q: | L4L | Planned order receipts | | | | | | | | 200 | | | | | Planned order releases | | | | | | | 200 | | | | Item: | C | Gross requirements | | | | | | | 300 | | | | OH: | 0 | Scheduled receipts | | | | | | | | | | | LT: | 1 | Projected available balance | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | SS: | 0 | Net requirements | | | | | | | 300 | | | | Q: | L4L | Planned order receipts | | | | | | | 300 | | | | | | Planned order releases | | | | | | 300 | | | | | Item: | D | Gross requirements | | | | | | | 400 | | | | OH: | 0 | Scheduled receipts | | | | | | | | | | | LT: | 1 | Projected available balance | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | SS: | 0 | Net requirements | | | | | | | 400 | | | | Q: | L4L | Planned order receipts | | | | | | | 400 | | | | | | Planned order releases | | | | | | 400 | | | | | Item: | E | Gross requirements | | | | | | 800 | | | | | OH: | 0 | Scheduled receipts | | | | | | | | | | | LT: | 3 | Projected available