Executive Summary
This sourcing strategy report represents the result of our analysis of four potential suppliers both domestic and international in an attempt of the company to outsource many key product components and subassemblies, including the 9000x series DVD drives. The identified suppliers include:
- Elecom Technologies: a global firm with solid reputation, and has price as a competitive edge. Their net sale is 1.5 times more than the other three suppliers combined.
- SureTech is a small firm, but located in the US, which will ensure shorter lead time, but has PSC would be their largest contract.
- E-Drive is a large firm and located locally, but has some issues lately with quality and technologies.
- Park Technologies is an …show more content…

E-Drive
- Has the most loosely credit policies, which has caused them to collect their receivables longer than the other ones.
- Normal compared in the industry, second highest return on equity of the four suppliers. E-drive has the best quick ratio with 1.04.
Park Technologies
- It is normal with the industry with everything ranged in the normal range, no obsolete ratio for further investigation.

Total cost analysis
Total Cost Analysis Worksheet - Year 1 (500,000 units)
Cost Category Elecom SureTech E-Drive Park
Quoted Unit Price 127 144 140 132
Transportation 18 $6 $14 $18
Tooling 6 7 6.5 7.5
Quality non-conformance costs
Duties/customs, insurance, and tariffs 11.5 1.5 3 $13
Inventory safety stock carrying charges:
Ordering, inbound receiving and inspection costs 4.5 4 3.25 2.25
Estimated Per Unit Total Cost 167 162.5 166.75 172.75
Lead time (weeks) 8 3 2 10

Taking into account of transportation and lead-time, the two international companies prices exceeded the prices of the two domestic after added transportation and duties/tariffs. after the financial and cost analysis, SureTech and E-Drive seems to be the best candidates. However, SureTech has a quick ratio of .7 as well as a smaller firm, E-Drive will be chosen with above average ratios, fastest lead time, 10 minutes away, and solid