Essay about Power Plant

2198 Words Sep 18th, 2014 9 Pages
Project Charter

Cambridge Bay, NWT
Power Generating Station Replacement

Submitted by:
Student #
MSTM4040 – Assignment #1
Feb 10, 2013

Table of Contents

Section 1. Charter Introduction 3
1.1 Document change control 3
1.2 Executive summary 3
1.3 Authorization 4
Section 2. Project Overview 5
2.1 Project summary 5
2.2 Project goals, business outcomes, and objectives 6
2.3 Project scope 6 2.3.1 Boundaries ………………………………………………………………………7
2.4 Milestones 8
2.5 Deliverables 8
2.6 Project cost estimate and sources of funding 9 2.6.1 Project cost Estimate …………………………………………………………….9 2.6.2 Sources of Funding ……………………………………………………………...9
2.7 Project risks, assumptions, and constraints 10
Section 3. Project
…show more content…
To develop a reliable source of electricity for Cambridge bay
Risks: working in remote location when building a large construction project, there are unknown cost involved. An important new risk is the cost of complying with potential greenhouse gas emission regulations. Sea lift delays and the potential of not having the contracts written on time and developed in detail.
Estimated total costs. 3 x 2 mega what generators - $1,500,000; Building - 2,000,000; auxiliary equipment- $1,000,000; other costs - $500,000
1.3 Authorization _______________________________________________ ____________________________
Lorne Kusugak Date
Executive Sponsor
Minister Responsible for Quilliq Energy Corp’s _______________________________________________ ____________________________
Simon Merkosak Date
Project Sponsor
Chair, Board of directors for Quilliq Energy Corp _______________________________________________ ____________________________
Peter Mackey Date
Project Manager
CEO Quilliq Energy Corp’s ______________________________________________ ____________________________ Frank Downey Date Project Engineer Quilliq Energy Corp’s _______________________________________________ ____________________________
John Smith Date
Mayor,