84 CHAPTER ELEVEN 11.19. A company that manufactures snow shovels has one plant and two distribution centers (DCs). Given the following information for the two DCs, calculate the gross requirements, projected available, and planned order releases for the two DCs and the gross requirements, projected available, and planned order releases for the central warehouse. Distribution Center A 2 weeks Transit Time: Order Quantity: 500 units 4 3 2 5 1 Week 275 150 300 200 300 Gross Requirements 500 In Transit 200 Projected Available Planned Order Release Distribution Center B 2 weeks Transit Time: Order Quantity: 200 units 5 4 3 2 1 Week 150 125 100 75 50 Gross Requirements In Transit 150 Projected Available Planned Order Release Central Supply 1 week Lead Time: Order Quantity: 600 units 5 Week 1 2 4 3 Gross Requirements Scheduled Receipts Projected Available 400 Planned Order Release

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter9: Decision Making Under Uncertainty
Section: Chapter Questions
Problem 46P
icon
Related questions
Question
84
CHAPTER ELEVEN
11.19. A company that manufactures snow shovels has one plant and two distribution
centers (DCs). Given the following information for the two DCs, calculate the
gross requirements, projected available, and planned order releases for the two DCs
and the gross requirements, projected available, and planned order releases for the
central warehouse.
Distribution Center A
2 weeks
Transit Time:
Order Quantity: 500 units
4
3
2
5
1
Week
275
150
300
200
300
Gross Requirements
500
In Transit
200
Projected Available
Planned Order Release
Distribution Center B
2 weeks
Transit Time:
Order Quantity: 200 units
5
4
3
2
1
Week
150
125
100
75
50
Gross Requirements
In Transit
150
Projected Available
Planned Order Release
Central Supply
1 week
Lead Time:
Order Quantity: 600 units
5
Week
1
2
4
3
Gross Requirements
Scheduled Receipts
Projected Available
400
Planned Order Release
Transcribed Image Text:84 CHAPTER ELEVEN 11.19. A company that manufactures snow shovels has one plant and two distribution centers (DCs). Given the following information for the two DCs, calculate the gross requirements, projected available, and planned order releases for the two DCs and the gross requirements, projected available, and planned order releases for the central warehouse. Distribution Center A 2 weeks Transit Time: Order Quantity: 500 units 4 3 2 5 1 Week 275 150 300 200 300 Gross Requirements 500 In Transit 200 Projected Available Planned Order Release Distribution Center B 2 weeks Transit Time: Order Quantity: 200 units 5 4 3 2 1 Week 150 125 100 75 50 Gross Requirements In Transit 150 Projected Available Planned Order Release Central Supply 1 week Lead Time: Order Quantity: 600 units 5 Week 1 2 4 3 Gross Requirements Scheduled Receipts Projected Available 400 Planned Order Release
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,