A building contractor is faced with the problems of possibly paying liquidated damages of $20,000.00 per day for the delay in the completion of work in accordance with the contract. The facts are as follows a. number of days left in the contract time is 30 days b. at present the working force are; 40 skilled workers with a daily wage of $700.00/day/worker 20 unskilled workers with a daily wage of P520.00/day/worker This is on an 8-hr day work. If he maintains the present number of men, he will finish the work in 50 days; overtime rate is 25% more than regular rate. Analyse/Answer the following cases: a. If he allows the present working force to work overtime for 2 hours a day, in how many days will he finish the work. How much are the savings or the loss? b. If the contractor puts additional men maintaining the ratio of two skilled workers to one unskilled in order to finish the work on time, how many workers will he add? No overtime work in this case. c. Should the contractor allow overtime work for two hours a day, how many men will he add in order to finish the work on time? How much will he save or loss?

Intermediate Algebra
19th Edition
ISBN:9780998625720
Author:Lynn Marecek
Publisher:Lynn Marecek
Chapter12: Sequences, Series And Binomial Theorem
Section12.3: Geometric Sequences And Series
Problem 12.58TI: What is the total effect on the economy of a government tax rebate of $500 to each household in...
icon
Related questions
Question

SOLVE THE QUESTION ACCURATELY WITH SOLUTION

A building contractor is faced with the problems of possibly paying liquidated damages of $20,000.00
per day for the delay in the completion of work in accordance with the contract.
The facts are as follows
a. number of days left in the contract time is 30 days
b. at present the working force are;
40 skilled workers with a daily wage of $700.00/day/worker
20 unskilled workers with a daily wage of P520.00/day/worker
This is on an 8-hr day work. If he maintains the present number of men, he will finish the work in 50
days; overtime rate is 25% more than regular rate.
Analyse/Answer the following cases:
a. If he allows the present working force to work overtime for 2 hours a day, in how many days will he finish
the work. How much are the savings or the loss?
b. If the contractor puts additional men maintaining the ratio of two skilled workers to one unskilled in order
to finish the work on time, how many workers will he add? No overtime work in this case.
c. Should the contractor allow overtime work for two hours a day, how many men will he add in order to
finish the work on time? How much will he save or loss?
Transcribed Image Text:A building contractor is faced with the problems of possibly paying liquidated damages of $20,000.00 per day for the delay in the completion of work in accordance with the contract. The facts are as follows a. number of days left in the contract time is 30 days b. at present the working force are; 40 skilled workers with a daily wage of $700.00/day/worker 20 unskilled workers with a daily wage of P520.00/day/worker This is on an 8-hr day work. If he maintains the present number of men, he will finish the work in 50 days; overtime rate is 25% more than regular rate. Analyse/Answer the following cases: a. If he allows the present working force to work overtime for 2 hours a day, in how many days will he finish the work. How much are the savings or the loss? b. If the contractor puts additional men maintaining the ratio of two skilled workers to one unskilled in order to finish the work on time, how many workers will he add? No overtime work in this case. c. Should the contractor allow overtime work for two hours a day, how many men will he add in order to finish the work on time? How much will he save or loss?
Expert Solution
steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Recommended textbooks for you
Intermediate Algebra
Intermediate Algebra
Algebra
ISBN:
9780998625720
Author:
Lynn Marecek
Publisher:
OpenStax College