Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity Description Immediate Predecessor Optimistic Most Probable Pessimistic A Report generation 2 9 13 B Web scraping 5 10 12 с Testing A, B 1 1 1 (a) Construct the project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen This answer has not been graded yet.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter13: Regression And Forecasting Models
Section13.4: Multiple Regression Models
Problem 12P
icon
Related questions
Question
You may need to use the appropriate technology to answer this question.
Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to
set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis.
Activity
A
B
C
Description
Report generation
Web scraping
Testing
Immediate
Predecessor
This answer has not been graded yet.
A, B
Optimistic
2
(d) Should you use the estimate in (b) or (c)?
5
1
Time (Weeks)
(a) Construct the project network. (Submit a file with a maximum size of 1 MB.)
Choose File No file chosen
Most Probable
9
10
1
Pessimistic
13
The probability estimate from (b) based on the critical path is more accurate.
The probability estimate from (c) based on both paths is more accurate.
O The probability estimates from (b) and (c) are equal.
12
(b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.)
1
(c) Using all paths through the project network, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.)
Transcribed Image Text:You may need to use the appropriate technology to answer this question. Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Activity A B C Description Report generation Web scraping Testing Immediate Predecessor This answer has not been graded yet. A, B Optimistic 2 (d) Should you use the estimate in (b) or (c)? 5 1 Time (Weeks) (a) Construct the project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen Most Probable 9 10 1 Pessimistic 13 The probability estimate from (b) based on the critical path is more accurate. The probability estimate from (c) based on both paths is more accurate. O The probability estimates from (b) and (c) are equal. 12 (b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) 1 (c) Using all paths through the project network, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 9 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

B and C are incorrect.

(b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.)
90.0820
X
(c) Using all paths through the project network, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.)
98.3970
X
Transcribed Image Text:(b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) 90.0820 X (c) Using all paths through the project network, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) 98.3970 X
Solution
Bartleby Expert
SEE SOLUTION