A landfill receives 10000tons/day of waste. This receipt rate increases  10% per year. The landfill is closed at the end of the fourth year. Using the exponential model calculate the yearly gas production for 20 years after opening. What is the peak peak gas production in m3/yr.

check_circleExpert Solution
Step 1

Consider landfill emission constant as 0.305 per year.

Consider generation potential as 100 m3/tonne.

Step 2

Find the mass of wet waste per year for year 1 using the relation;

M (10,000tonnes/day) 365 days
1 year
10,000x 365 tonnes/day
=3,650,000 tonnes/day
help_outline

Image Transcriptionclose

M (10,000tonnes/day) 365 days 1 year 10,000x 365 tonnes/day =3,650,000 tonnes/day

fullscreen
Step 3

Calculate the mass of wet waste per year for year 2, 3, and 4 by adding 10 % increment of receipt rate.

Similarly, calculate and...

Year Mass of wet waste per year (tons)
3,650,000
4,015,000
4,416,500
4,858,150
1
2
3
4
Sum
16,939,650
help_outline

Image Transcriptionclose

Year Mass of wet waste per year (tons) 3,650,000 4,015,000 4,416,500 4,858,150 1 2 3 4 Sum 16,939,650

fullscreen

Want to see the full answer?

See Solution

Check out a sample Q&A here.

Want to see this answer and more?

Solutions are written by subject experts who are available 24/7. Questions are typically answered within 1 hour*

See Solution
*Response times may vary by subject and question
Tagged in

Engineering

Civil Engineering

Related Civil Engineering Q&A

Find answers to questions asked by student like you

Show more Q&A add
question_answer

Q: A dilatometer test was conducted in a sand deposit ata depth of 6 m. The groundwater table was locat...

A: Following is the figure fetched from the given information.

question_answer

Q: Fluid Mechanics I tried to get a jar of Mexican chocolate mole' sauce through an airport TSA officer...

A: We have been given the following information,Density of  Mexican chocolate mole sauce =  7000 kg/m3B...

question_answer

Q: subject: Geotechnical Engineeringbook: principle of foundation engineering - Braja M Das

A: Given:

question_answer

Q: 7.7 The center of gravity of the 50-kg spool is at G. A cable wound around the hub of the spool is a...

A: “Hey, since there are multiple questions posted, we will answer first question. If you want any spec...

question_answer

Q: Estimate the life of a landfill for a user population of 10,000. The available area for the are-type...

A: Consider the rate of per capita generation is 4.5 lb./(person/day)Consider the landfill density is 1...

question_answer

Q: The wall is 15 ft high and consists of 2*4 in. Studs, plastered on one side. On the other side there...

A: Take the minimum design load of 2x4 in. studs plastered on one side is 12 psf.Take the minimum desig...

question_answer

Q: Give one or two possible identifications for each of the following. Provide a group symbol and descr...

A: Solution to the given scenario:Generally the soil is divided into three types based on their size su...

question_answer

Q: the stall has a flat roof with a slope of 40 mm/m. it is located in an open field where the ground s...

A: We have given the following data:Slope = 40 mm/mGround snow load (Pg)= 0.84 KN/m2

question_answer

Q: What is a hydrometer reading?

A: A hydrometer is an instrument used for the determination of the specific gravity of liquids. A speci...