A production process at Kenneth Day Manufacturing is shown in the figure. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. The product then goes to the welding station and finally the product needs to go through only one of the three assembly operations (the operations are in parallel).   The capacity of the sawing station is 2.4 units per hour. The capacity of the sanding station is 1.8 units per hour. The capacity of the drilling station is 7 units per hour. The capacity of the welding station is 6 units per hour. Each of the three assembly stations has a capacity of 0.7 units per hour. ​a) Sanding is the bottleneck.   ​b) The bottleneck time is 33.33 minutes per unit ​   ​c) The throughput time of the overall system is = ? ? ? minutes ​(round your response to two decimal​ places).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
A production process at Kenneth Day Manufacturing is shown in the figure. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. The product then goes to the welding station and finally the product needs to go through only one of the three assembly operations (the operations are in parallel).
 
The capacity of the sawing station is 2.4 units per hour.
The capacity of the sanding station is 1.8 units per hour.
The capacity of the drilling station is 7 units per hour.
The capacity of the welding station is 6 units per hour.
Each of the three assembly stations has a capacity of 0.7 units per hour.

​a) Sanding is the bottleneck.
 
​b) The bottleneck time is 33.33 minutes per unit ​
 
​c) The throughput time of the overall system is
= ? ? ?
minutes ​(round your response to two decimal​ places).
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

​d) If the firm operates 11 hours per​ day, 20 days per​ month, the monthly capacity of the manufacturing process is ??? units ​(enter your response as a whole​ number).

Solution
Bartleby Expert
SEE SOLUTION
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,