Boise Lumber has decided to enter the lucrative prefabricated housing business. Initially, it plans to offer three models: standard, deluxe, and luxury. Each house is prefabricated and partially assembled in the factory, and the final assembly is completed on site. The dollar amount of building material required, the amount of labor required in the factory for prefabrication and partial assembly, the amount of on-site labor required, and the profit per unit are as follows. Standard Model Luxury Model $10,000 Deluxe Model Material $6,000 $8,000 Factory Labor (hr) On-Site Labor (hr) 240 220 200 180 210 300 Profit $3,400 $4,000 $5,000 For the first year's production, a sum of $8,200,000 is budgeted for the building material; the number of labor-hours available for work in the factory is not to exceed 215,000 hr; and the amount of labor for on-site work is to be less than or equal to 237,000 labor-hours. Determine how many houses of each type Boise should produce to maximize its profit from this new venture. standard model houses deluxe model houses luxury model houses

College Algebra (MindTap Course List)
12th Edition
ISBN:9781305652231
Author:R. David Gustafson, Jeff Hughes
Publisher:R. David Gustafson, Jeff Hughes
Chapter6: Linear Systems
Section6.8: Linear Programming
Problem 5SC: If during the following year it is predicted that each comedy skit will generate 30 thousand and...
icon
Related questions
Question
Boise Lumber has decided to enter the lucrative prefabricated housing business. Initially, it plans to offer three models: standard, deluxe, and luxury. Each house is prefabricated and partially
assembled in the factory, and the final assembly is completed on site. The dollar amount of building material required, the amount of labor required in the factory for prefabrication and partial
assembly, the amount of on-site labor required, and the profit per unit are as follows.
Standard Model
Luxury Model
$10,000
Deluxe Model
Material
$6,000
$8,000
Factory Labor (hr)
On-Site Labor (hr)
240
220
200
180
210
300
Profit
$3,400
$4,000
$5,000
For the first year's production, a sum of $8,200,000 is budgeted for the building material; the number of labor-hours available for work in the factory is not to exceed 215,000 hr; and the amount of
labor for on-site work is to be less than or equal to 237,000 labor-hours. Determine how many houses of each type Boise should produce to maximize its profit from this new venture.
standard model
houses
deluxe model
houses
luxury model
houses
Transcribed Image Text:Boise Lumber has decided to enter the lucrative prefabricated housing business. Initially, it plans to offer three models: standard, deluxe, and luxury. Each house is prefabricated and partially assembled in the factory, and the final assembly is completed on site. The dollar amount of building material required, the amount of labor required in the factory for prefabrication and partial assembly, the amount of on-site labor required, and the profit per unit are as follows. Standard Model Luxury Model $10,000 Deluxe Model Material $6,000 $8,000 Factory Labor (hr) On-Site Labor (hr) 240 220 200 180 210 300 Profit $3,400 $4,000 $5,000 For the first year's production, a sum of $8,200,000 is budgeted for the building material; the number of labor-hours available for work in the factory is not to exceed 215,000 hr; and the amount of labor for on-site work is to be less than or equal to 237,000 labor-hours. Determine how many houses of each type Boise should produce to maximize its profit from this new venture. standard model houses deluxe model houses luxury model houses
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 7 steps with 7 images

Blurred answer