Boisjoly Enterprises is considering buying a vacant lot that sells for $1.4 million. If the property is purchased, the company’s plan is to spend another $6 million todayto build a hotel on the property. The cash flows from the hotel will depend critically on whether the state imposes a tourism tax in this year’s legislative session. If the tax is imposed, the hotel is expected to produce cash flows of $500,000 at the end of each of the next 15 years. If the tax is not imposed, the hotel is expected to produce cash flows of $1,200,000 at the end of each of the next 15 years. The project has a 12% WACC. Assume at the outset that the company does not have the option to delay the project.   1.What is the project’s expected NPV if the tax is imposed? 2.What is the project’s expected NPV if the tax is not imposed? 3.Given that there is a 45% chance that the tax will be imposed, what is the project’s expected NPV if management proceeds with it today? 4.Although the company does not have an option to delay construction, it does have the option to abandon the project 1 year from now if the tax is imposed. If it abandons the project, it will sell the complete property 1 year from now at an expected price of $7 million after taxes. Once the project is abandoned, the

EBK CONTEMPORARY FINANCIAL MANAGEMENT
14th Edition
ISBN:9781337514835
Author:MOYER
Publisher:MOYER
Chapter10: Capital Budgeting: Decision Criteria And Real Option
Section: Chapter Questions
Problem 14P
icon
Related questions
Question

Boisjoly Enterprises is considering buying a vacant lot that sells for $1.4 million. If the property is purchased, the company’s plan is to spend another $6 million todayto build a hotel on the property. The cash flows from the hotel will depend critically on whether the state imposes a tourism tax in this year’s legislative session. If the tax is imposed, the hotel is expected to produce cash flows of $500,000 at the end of each of the next 15 years. If the tax is not imposed, the hotel is expected to produce cash flows of $1,200,000 at the end of each of the next 15 years. The project has a 12% WACC. Assume at the outset that the company does not have the option to delay the project.

 

1.What is the project’s expected NPV if the tax is imposed?

2.What is the project’s expected NPV if the tax is not imposed?

3.Given that there is a 45% chance that the tax will be imposed, what is the project’s expected NPV if management proceeds with it today?

4.Although the company does not have an option to delay construction, it does have the option to abandon the project 1 year from now if the tax is imposed. If it abandons the project, it will sell the complete property 1 year from now at an expected price of $7 million after taxes. Once the project is abandoned, the

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

Although the company does not have an option to delay construction, it does have the option to abandon the project 1 year from now if the tax is imposed. If it abandons the project, it will sell the complete property 1 year from now at an expected price of $7 million after taxes. Once the project is abandoned, the company will no longer receive any cash flows. Assuming that all cash flows are discounted at 12%, will the existence of this abandonment option affect the company’s decision to proceed with the project today? Explain.

Solution
Bartleby Expert
SEE SOLUTION
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Corporate Fin Focused Approach
Corporate Fin Focused Approach
Finance
ISBN:
9781285660516
Author:
EHRHARDT
Publisher:
Cengage
Excel Applications for Accounting Principles
Excel Applications for Accounting Principles
Accounting
ISBN:
9781111581565
Author:
Gaylord N. Smith
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage