Consider the following activity diagram (partial): A (8) (4) (8) Following additional information is available: Activity A, ES = 6; LS = 6 Activity B, ES 5; LS = 10 What will be the ES value for C? a) 10 b) 13 c) 14 d) 6
Q: Draw the network and identify the critical path. Also calculate the earliest-latest starting and…
A: The method used for scheduling a set of activities that form part of a project, is called critical…
Q: The Figure 1 below shows the activities on the nodes, while the table shows the normal time, crash…
A: There are two separate paths. The duration of the paths is: Start–A–B–F–End = 18 days…
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Expected Time= a+4m+b6 Where a= Optimistic time b= Pessimistic time m = Most…
Q: Activity Preceding activity Optimistic Most Pessimistic Likely A 3 8 A 1 3 C A 11 D 4 3 4 В, С В, D…
A: A - 3 6 8 B A 1 3 5 C A 2 2 11 D C 4 3 4 E B, C 3 5 4 F B, D 5 2 2 G E, F 3 6 12…
Q: a. Draw the project network diagram. b. What completion date would you recommend?
A: Below is the solution:-
Q: Consider the following project activities with a normal unit: (The normal unit is Day) Activity…
A: Network Diagram :
Q: 1- The network below represents a project being analyzed by Critical Path Methods. Activity…
A: Since you have submitted questions with multiple subparts, as per guidelines we have answered the…
Q: b) - Draw the Activity-on-Node (AON) diagram using the following representation for every node:…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: The activity details and their predecessors are given below along with their activity times.…
A: The construction of the network is very important to understand the flow of activities in the…
Q: The following information is available about a project to organize an event to honor the mayor of…
A: a.
Q: Based on the set of activities below Description Task Must Follow Time (Weeks) Draw data flow A None…
A: PERT Diagram: Kindly find the PERT diagram below: Calculation methods: Assume 0 for start…
Q: Draw the arrow diagram, using the helpful numbering of the activities, which suggests the following…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: a. The Consolidated Bank of Ghana (CBG) is planning to install a new computerized accounts system.…
A: A network diagram is a graphical representation of a project that identify the activity relationship…
Q: The activities necessary for the completion of this project are listed in the following table:…
A: Since you have posted a question with multiple sub-parts, we will solve the subparts asked by you.…
Q: An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and…
A: We have, Optimistic, To = 2 Most likely, Tm = 3 Pessimistic, Tp = 6
Q: using the PERT formula calculate the time value for each activity and construct the network diagram
A: A PERT diagram is a project management took which enables to understand the relationship between…
Q: Activity (day) Predecessor(s) A 6…
A: Given data is
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Given data is
Q: 12. Given the following network project where the times are in days: Task Normal Crash Normal Crash…
A: Given data: TASK NORMAL TIME CRASH TIME NORMAL COST CRASH COST IP A 2 1 200 300 - B 3 1 100…
Q: The information in the table below is available for a large fund-raising project. Activity…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: The following Table 1 (below) contains a list of activities, with precedence requirements and crash…
A: Find the Given details below: Activity Predecessors Normal Time (NT) (Days) Normal cost (NC) ($)…
Q: Time (weeks) Immediate Time (weeks) Immediate Activity Predecessor(s) Activity Predecessor(s) a a A…
A: Estimated activity periods are not guaranteed when doing Critical Path calculations. This date is…
Q: a)Construct AON diagram for the following data. b) Identify path, path duration and critical path c)…
A: Below is the solution:-
Q: The following information is available about a project to organize an event to honor the mayor of…
A:
Q: Activity Times (days) Activity Cost ($) Immediate Activity Predecessor 100 None 150 None 125 А D 175…
A: given,
Q: a) Draw the AON project network diagram. b) Calculate the expected time of each activity? (Round…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Make a list of the tasks that is necessary for Management Trainee Officer job in private banks.…
A: Below is the solution:-
Q: 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each…
A: The project network is the visual representation of the project activities and their durations to…
Q: Table 7.4 Activity Predecessor Time(weeks) 8. B 6. 4. D A 11 B 3 G D, E, F 1 1) Using Table 7.4,…
A: 1) The earliest time for completion for this project is 20 weeks so the answer is C)20 weeks
Q: 2. Given the data, answer the questions below. Activity Normal Time Normal Cost Crashed Time Crashed…
A: Find the Given details below: Activity Normal Time (NT) (Weeks) Normal cost (NC) (Pesos) Crash…
Q: • 3.12 The activities needed to build a prototype laser scan- ning machine at Dave Fletcher Corp.…
A: The following information is given:
Q: Q3: Draw the network diagram and determine the critical path for the following project: Activity…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Find the given details below: Activity Dependency Optimistic Time(To) a(Weeks) Pessimistic…
Q: 1. a. The following Table 1 (below) contains a list of activities, with precedence requirements and…
A: prepare a network diagram for above details as shown below:
Q: a. Draw a precedence diagram using AOA , AON and Gantt chart. b. Find the critical path using CPM.…
A: Below is the solution:-
Q: b) Provide a brief explanation of the main difference between a Work Breakdown Structure and Network…
A: A project network diagram is shown as a chart with a sequence of boxes and arrows.
Q: EXAMPLE 4: (H.W) Determine the critical path of the following table using the Gantt chart. 25 ,7…
A: In this question, we have got the table data that includes activity ID, Predecessor information and…
Q: 1. Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you…
A: Hello thank you for the question. As per guidelines, we would provide only one answer at a time.…
Q: The following Table 1 contains a list of activities, with precedence requirements and crash costs.…
A: The network diagram is shown below
Q: Two
A: The formula for EF = Max (EF of all immediate predecessors)Since C is preceded by A and B we find…
Q: 2. A project for improving a billing process has the following precedence relationships and activity…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: A Social Project manager is faced with a project with the following activities: Activity-ID…
A: Given data is
Q: PERT-CPM 1. Consider a project involving the following activities and precedence relationship. The…
A:
Q: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: Given data is
Q: The following Table 1 (below) contains a list of activities, with precedence requirements and crash…
A: Find the Given details below: Activity Predecessors Normal Time (NT) (Days) Normal cost (NC) ($)…
Q: What is the slack time for activity A? 7 5 3 0
A: Formula:
Q: Activity b Immediate a m Predecessor (days) A 3 5 B 0.5 1 1.5 A C D 4 A 5 7 9 B E 1 2 3 F 6. 9 12 D…
A: Given data is
Q: Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with…
A: Find the given details below: Activity ImmediatePredecessors Duration(Days) A - 44 B - 35 C…
Q: Q2. Consider the following data summarizing the details of a project involving 12 activities.…
A:
Q: A student club plans on holding a campus-wide event at the end of the semester. The activities that…
A: Given that: Duration Immediate Activity (weeks) Predecessor A 2 -- B 3 A C 1 A D 3…
One
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Consider the following activity description with associated cost data shown in Table 1. The cost data represents the total cost and should be considered linear with time. Table 1: Crash Cost Table Activity Immediate Predecessor Normal Duration (days) Normal Cost ($) Crash Duration (days) Crash Cost ($) A --- 5 50 3 150 B --- 4 40 2 200 C B 7 70 5 250 D A, C 2 20 1 50 E A, C 5 125 1 525 F B 10 80 7 290 G D 7 50 3 250 H E, F 6 60 3 180 Reduce the project duration to minimum duration and calculate the cost. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.Table 7.8 contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $15,000 per week, and a penalty cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week 9.a. What is the shortest time duration for this project regardless of cost?b. What is the minimum total cost associated with completing the project in 9 weeks?c. What is the total time of the minimum-cost schedule?1. For the following Activity table draw the CPM diagram Using Activity On Node. Show the ES, LS, EF, LF and Slack for each activity on the diagram. Indicate the Critical path. Activity Time (Days) Predecessor A 4 ------------ B 7 A C 8 A D 2…
- Draw a network diagram showing the linkage between these activities from start to finish. For the diagram, each activity should be labelled alphabetically ie. A, B, C… etc. PERT Formula: TE = (O + 4T + P) / 6 TE = Pert Expected Time Duration, O = Optimistic estimate, P = Pessimistic estimate, T = Most Likely (Typical) estimate Activity Predecessor Optimistic Most Likely Pessimistic Duration Duration in Weeks A — 2 3 4 B — 4 5 7 C B 1 2 3 D C & E 0.5 1 1.5 E B 0.5 1 1.5 F C 2 3 4 G F 2 3 4Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 33 B Develop Client Prospectus ― 21 C Perform Design Analysis ― 35 D Program Back End A, B, C 47 E Program Front End A 13 F Project Consolidation D, E 11 (a) For the given project, fill in the nodes of the network diagram below. A E 33 13 Start B D F Finish Time 21 47 11 Time C 35 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…Draw the PDM network diagram for the following project, calculate the earliest and latest starting and finishing times for all activities, and hence calculate the total float, free float for each activity. Activity IPA Duration (WEEKS) WORKERS REQUIRED PER WEEK EQUIPMENT REQUIRED (hrs/WEEK) H ---- 10 5 8 I H 8 4 2 J H 6 8 6 K J 4 2 1 L J 2 6 2 M J 4 3 2 N I 4 2 0 O I 5 5 0 P I, J 5 6 6 Q L 5 2 0 R M 5 0 4 S N 3 0 4 T Q 3 0 0 U O, S 1 9 8 V K, R 5 14 8 W U 2 6 8 X V 3 6 8 Y P,W,X,T 8 14 8 Z Y 6 5 8 If there is a limit of 15 workers per week, smooth the workers loading using ES and LS histogram. Based on the proposed scheduling, plot the equipment loading histogram for the project. Independently of the above resource leveling, schedule the…
- For data given below draw an AON diagram and calculate ES, EF, LS, LF and Slack? Activity Duration Immediate Predecessor A 2 - B 3 - C 5 A D 9 B E 5 C,D F 5 D G 2 E2. a) The activity shown in Table Q2 (a) are processes carried out in a mechatronic company. Based on the table provided, (i) Determine the Critical Path and Project Duration to complete the process. ii. Activity F cannot start immediately after activity C. The delay is expected to be 7 days. Determine by stating the possible problem, Critical Path and Project Duration to complete the process.Activity on Arrows : Questions1. Organize the information above in an activity precedence table.2. Draw an Activity-On-Arrow (AOA) network diagram representing information shown onthe activity precedence table.3. Show all different paths and their durations
- For the next project: | | TIME ESTIMATE (WEEKS) TASK DESCRIPTION a m b A foundations 2 3 4 B framework 4 7.5 8 C roofs 3 5.5 11 D plumbing 2.5 4 5.5 E electrical wiring 2 3 4 F doors and windows 3 5 7 G interior finish 3 3.5 7 H exterior finish 2 5 8 I inspection 1 1 1 a. I made the network diagram. b. Calculate the parameters corresponding to expected time, variance, nearest and farthest start times and farthest c. What is the probability of meeting a specific project completion date? For example, what is the probability of building the house in 32 weeks? Topic: stochastic processes3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: a) DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team. b) Find the critical path. c) What is the project completion time? • • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede: ACTIVITY DURATION (WEEKS) PRECEDES A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 — ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A — 2 B — 5 C — 1 D B…10. The project described in the following table is scheduled to be completed in 11 weeks. Constructa network diagram using AOA or AON (see Example 5 for either type). Then answer the followingquestions:a. If you were the manager of this project, would you be concerned? Explain.b. If there is a penalty of $5,000 a week for each week the project is late, what is the probabilityof incurring a penalty of at least $5,000? Path Activity Estimated time(Weeks) Std. Dev(Wks) A C 4 0.7 D 6 0.9 B E 3 0.62 F 9 1.9