Consider the following linear programming problem: Maximize 12X + 10Y Subject to: 4X + 3Y = 480 2X + 3Y 360 = all variables 20 Which of the following points (X,Y) is not feasible? a (70,70) b. (20,90) أجرب الأرقام بالـؤال
Q: Activities' estimated duration and the time intervals at which the actual progress is analyzed…
A: An activity's estimated duration can be defined as the approximated time that will be taken by a…
Q: a) The correct precedence relationship with one of the possible assignment of tasks to workstations…
A: Project schedule helps in calculating different values all related to the production cycle like the…
Q: Sycamore Plastics (SP) is a manufacturer of polyethylene plastic pellets used as a raw material by…
A: Solver constraints:
Q: The table below shows the sales figures for a brand of shoe over the last 12 months. Months January…
A: Forecasting method is the method that determines the future values according to the previous years'…
Q: Importance of Quality control and Quality assurance for the national and international…
A: Quality control and quality assurance are important for national and international accreditation.…
Q: My Happy Feet Company manufactures athletic shoes. The company wants to establish a p chart to…
A: Find the Calculation methods below: Fraction Defectives = Number of DefectivesSample sizeCentral…
Q: 2. Find the initial basic feasible solution of the following Transportation Problem by NWCR. The…
A: The northwest corner method is a problem-solving technique that is used in operations management.…
Q: Assume that total sales revenue for 2018 is projected to be $1,290,518. Assume also the following…
A: Given, Total sales revenue = $1,290,518 NMC = Net Market Contribution / Total sales revenue Net…
Q: Identify and explain four assumptions of the economic order quantity
A: Economic order quantity : Economic order quantity is necessary to minimize order-related and the…
Q: Explain any two process technologies for materials
A: Process Technologies: Process technologies differ based on the nature of materials.…
Q: Tyler Apiaries sells bees and beekeeping supplies. Bees (including a queen) are shipped in special…
A: Given data: Target weight μ =14 kg Tolerance limit =+/- 2.4 kg Standard deviationσ= 0.7 kg
Q: 4. It takes Susan 30 minutes to solder 10 circuit boards to fill a container and 2 minutes to…
A: NOTE: We are allowed to do one question only. Ans 4. Given: no.of kanbans K 5 processing…
Q: Can we use CPFR in SMEs?
A: CPFR stands for Collaborative Planning Forecasting and Replenishment. Participants in a supply chain…
Q: Bindley Corporation has a one-year contract to supply motors for all washing machines produced by…
A: Build transportation grid as follows.
Q: Define the supply chains for the following products from the first source of raw materials to the…
A: Production is the process of transforming the raw materials into the finished products and services…
Q: . Using trend projection, develop a formula to predict sales for years 11 and 12. You have to show…
A: Slope can be calculated as: b=(n∑xy-∑ x∑ y)/(n∑ x^2-(∑ x)^2 ) Intercept can be calculated as: a=(∑…
Q: If partway through the project we discover that more money has actually been spent to that point…
A: In this scenario, CV and EV come in handy. The project budget and cost variation are directly…
Q: Question sti Saved All of the following can be said about network diagrams EXCEPT: For making a…
A: A : For making a network...... This is false because there is no such constraint to represent a…
Q: Truck 1 2 3 4 5 A46756 354325 B 5 Route с 9 8 10 5 3 A63454 Ꭰ 8 E75689 10
A: Given data:
Q: Mr. John produces a special type of shoes on an assembly line. The process involves eight different…
A: Necessary information: The following information is required to balance the assembly line. these are…
Q: The following information relates to a project (task times are in weeks). Use the information to…
A: Given, Desired completion time X= 36 weeks Formulae: Expected time μ= (to+4*tm+tp)/6 Variance =…
Q: Give some examples of automation. How has automation changed the production process?
A: Conveyor belts, robotic arms, and complex machinery come to mind when picturing a production plant,…
Q: 4. Solve the precedence diagram network shown below. Compute the values of ES, EF, LS, LF, FF, and…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: need help with the critical path method. I want to do the critical path, slack times, and all…
A: The critical path is a term used in project management to describe the sequence of tasks that must…
Q: How is quality control of a project different from quality control of a manufacturing process?
A: The term "Quality" refers to how good or bad is the resultant output. It defines a state or a…
Q: Suppose that a task in a project has the following time estimates: to=optimistic completion…
A: Given data: Optimistic time period (to) = 10 weeks Most likely completion period (tm) =17 weeks…
Q: Amelio Rodríguez Computing wants to establish an assembly line for producing a new product, the…
A: Given, Target = 180 PDAs per hour Available time = 1 hour = 3600 seconds
Q: Baton Rouge's Mt. Cedar Hospital is a large, private, 600-bed facility complete with…
A: Based on the given information, the decision variables are X1 and X2. Here, the revenue details are…
Q: Over what range of output is location A the most preferred location? 2. Over what range of output…
A: (1) From the given table, Location A seems to be lowest cost at 2000 units. And it is not the…
Q: curement cycle 2. List ways in which each component could be corrupted 3. Identify possible…
A: Procurement is a catch-all phrase for all aspects of purchasing, ranging from vendor selection and…
Q: what the norms a negotiator might use to justify a position
A: People take positions and express their interests during negotiations. A party's specific demands at…
Q: The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is…
A: Precedence Diagram - is a pictorial representation method that shows the activities concerned in the…
Q: The following table shows the number of televisions sold over the last ten years at a local…
A: Assume Year = X and TV Sales = Y. Trend Projection Forecasting: Calculate X*Y and also X^2 for the…
Q: A chart used to accent the size of change is called:
A: Column chart:- The data is shown in the rectangular bars with the height proportionate to the…
Q: Item A has a gross requirement of 2,400 in week 6. Currently, there are 200 Item A's on hand with…
A: Given, Gross requirement in week 6 = 2400 On hand inventory in week 1 = 200 Scheduled receipts in…
Q: K Race One Motors is an Indonesian car manufacturer. At its largest manufacturing facility, in…
A: Economic order quantity is an order quantity that use to define the optimal quantity of orders to…
Q: The marketing department of a soft drink company wishes to determine the maximum expected payoff…
A: Extremely optimistic decision making means maximax criteria. Maximax criteria = maximum payoff of…
Q: Explain the three different source of information and forecast assumptions
A: The term "forecasting" describes the process of speculating on what will occur in the future based…
Q: The optimistic, most likely and pessimistic times for the tasks comprising a project are shown…
A: Expected time te= (to+4*tm+tp)/6 Variance s2t= ((tp-to)/6)2 Task to tm tp A 5 10…
Q: Mr. Jack is in the process of expanding his manufacturing business. He decided to open a plant in…
A: Find the Calculations below: Total cost = (Fixed cost + (Number of units * Variable Cost)) Cost…
Q: A call center manager wants to track the number of mistakes that her staff makes on a daily basis.…
A: Given: Monday = 12 Tuesday = 20 Wednesday= 8 Thursday = 10 Friday = 18
Q: Forecast accuracy is important because it impacts the organizations' money and people. True False
A: Accurate forecasting helps with cost cutting, production and staff scheduling, capital planning and…
Q: Cesar Rego Computers, a Mississippi chain of computer hardware and software retail outlets, supplies…
A: Given, Annual demand D = 36100 disks Order cost S = $25 Holding cost = I * Purchase price =…
Q: The types of charts that can show three dimensions are: O doughnut charts Obubble charts surface…
A: Charts, histograms, bar graphs etc are various kinds of diagrams used to represent data. These…
Q: what do I mean when I say that inventory costing methods are not related to the physical flow of…
A: The price per unit of goods acquired might vary. Hence it is crucial for retailing, manufacturing,…
Q: the number of persuasive messages has increased drastically within the last decade? 1. True 2.…
A: A compelling message is the main idea that engages, educates, persuades, or motivates. Discussions…
Q: The Talbot Company uses electrical assemblies to produce an array of small appliances. One of the…
A: Given Data: Annual demand (D) = 11000 units Ordering cost (S) =$500 Holding Cost (H)=$20 per year…
Q: Amazon Equipment Vendor Exercise An Amazon vendor has 10,000 square feet of warehouse space. The…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: Expected Time fot the critical path on a PERT network is 18.2 weeks, and the critical path variance…
A: Find the Calculation methods below: Probability = Projected time - Actual durationStandard…
Q: Oakwood Hospital is considering using ABC analysis to classify laboratory SKUs into three…
A: Formulae used: To determine the Annual dollar usage: Annual dollar usage = Unit value × Demand
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
- b) Maximize Z = −40X1 −100X2s.t 10X1 + 5X2 ≤ 2502X1 + 5X2 ≤ 1002X1 + 3X2 ≤ 90X1, X2 ≥ 0Solve by simplex method, what are the solutions? Show that this problem hasmultiple solutions and find the solutions?Set up the simplex matrix used to solve the linear programming problem. Assume all variables are nonnegative. Maximize f = 8x + 9y + 3z subject to 2x + 7y + 8z ≤ 100 6x + 3y + z ≤ 160 3x + 4y + 9z ≤ 10 .Find the values of x1 and x2 where the following two constraints intersect. (Round your answers to 3 decimal places.) (1) 10x1 + 5x2 ≥ 50 (2) 1x1 + 2x2 ≥ 12
- Analyze algebraically what special case in simplex application is present in each of the LP model below. Give an explanation to support your answer. a) Maximize z = 4x1 + 2x2 Subject to: 2x1 - x2 ≤ 2 3x1 - 4x2 ≤ 8 x1, x2 ≥ 0b) Maximize z = 3x1 + 2x2 Subject to: 4x1 - x2 ≤ 8 4x1 + 3x2 ≤ 12 4x1 + x2 ≤ 8 x1, x2 ≥ 0For the products A, B, C, and D, which of the following could be a linear programming objective function? Select one: a. Z = 1A + 2BC + 3D b. Z = 1A + 2AB + 3ABC + 4ABCD c. Z = 1A + 2B + 3C + 4D d. Z = 1A + 2B/C + 3DUse the simplex method to maximize the given function. Assume all variables are nonnegative. Maximize f = 7x + 14y + 4z subject to the following. 3x + 5y + 4z ≤ 30 3x + 2y ≤ 4 x + 2y ≤ 8 (x,y,z)= f=
- A decision problem has the following three constraints: 70X + 6Y <= 420; 24X + 3Y= 72; and 11X - Y <= 14 . The objective function is Min 17X + 38Y . The objective function value is : a. 338 b. 676 c. unbounded d. infeasible e. 0Given this linear programming model, solve the model and then answer the questions that follow.Maximize Z = 12x1 + 18x2 + 15x3 where x1 = the quantity of product 1 to make, etc.Subject toMachine 5x1 + 4x2 + 3x3 ≤ 160 minutes Labor 4x1 + 10x2 + 4x3 ≤ 288 hoursMaterials 2x1 + 2x2 + 4x3 ≤ 200 poundsProduct 2 x2 ≤ 16 units x1, x2, x3 ≥ 0 a. Are any constraints binding? If so, which one(s)?Find the indicated maximum or minimum value of the objective function in the linear programming problem. Minimize g = 10x + 6y subject to the following. x + 2y ≥ 10 2x + y ≥ 11 x + y ≥ 9 x ≥ 0, y ≥ 0
- We have 60 meters of fence and want to fence a triangular shaped area. Please formulate an NLP (do not try to solve) that will enable us to maximize the fenced area (Hint: The area of a triangle with sides of length a, b, and c is ( s (s – a) (s – b) (s – c))1/2, where s is half the parameter of the triangle).Consider the following LP problem developed at Zafar Malik's Carbondale, Illinois, optical scanning firm: Maximize Z= 1X1+1X2 Subject to: 2X1+1X2≤72 (C1) 1X1+2X2≤72 (C2) X1,X2≥04. Consider the following linear programming problem: Maximize Z=$15x + $5y, subject to (1) 2x + y ≤ 10 and (2) 4x + 3y ≤ 24 and (3) x, y ≥ 0. Will the optimal solution change if the objective function becomes Maximize Z=$15x + $20y (constraints remain the same)? Select one: a. Can't determine given the information. b. Yes, it will change. c. No, it remains the same.