Develop a resource schedule using as your template the loading chart below. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Note: activities use the resource skills as shown in the network diagram. Four of the resource skills are available.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
List the order in which you scheduled the activities of the project.
First
Second
Third
Fourth
Fifth
Sixth
Recompute your slack for each activity given your new schedule. What is the slack for:
Activity 1
Activity 4
Activity 5
What is the expected length of the project considering resources?
The expected length of the project
Transcribed Image Text:List the order in which you scheduled the activities of the project. First Second Third Fourth Fifth Sixth Recompute your slack for each activity given your new schedule. What is the slack for: Activity 1 Activity 4 Activity 5 What is the expected length of the project considering resources? The expected length of the project
Develop a resource schedule using as your template the loading chart below. Use the parallel method and heuristics given. Be sure to
update each period as the computer would do. Note: activities use the resource skills as shown in the network diagram. Four of the
resource skills are available.
016
03 0
066
02 5
2 1
5 6
1
1
ID
1
2
3
4
5
6
6 3 10
111
7 4 11
6 4 11
0 1
5
3
2
0
6 5 11
5
5 8
3 2 3
8
3 11
Legend
ES ID EF
SLK RES SLK
LS DUR LF
11 6 13
020
11 2 13
Schedule resource load chart with ES and slack updates
Resource Duration ES LF SL TP 1 TP 2 TP 3 TP 4 TP 5 TP 6 TP 7 TP 8 TP 9 TP 10 TP 11 TP 12 TP 13 TP 14 TP 15
3
6
06 0
2
5
06 1
1
4
6 11 1
1
6 11 0
2
5 11 3
2
11 13 0
Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has been shaded. Any
resource scheduled beyond the shaded area will delay the project. "TP" stands for time period.
Transcribed Image Text:Develop a resource schedule using as your template the loading chart below. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Note: activities use the resource skills as shown in the network diagram. Four of the resource skills are available. 016 03 0 066 02 5 2 1 5 6 1 1 ID 1 2 3 4 5 6 6 3 10 111 7 4 11 6 4 11 0 1 5 3 2 0 6 5 11 5 5 8 3 2 3 8 3 11 Legend ES ID EF SLK RES SLK LS DUR LF 11 6 13 020 11 2 13 Schedule resource load chart with ES and slack updates Resource Duration ES LF SL TP 1 TP 2 TP 3 TP 4 TP 5 TP 6 TP 7 TP 8 TP 9 TP 10 TP 11 TP 12 TP 13 TP 14 TP 15 3 6 06 0 2 5 06 1 1 4 6 11 1 1 6 11 0 2 5 11 3 2 11 13 0 Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has been shaded. Any resource scheduled beyond the shaded area will delay the project. "TP" stands for time period.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,