Given the following diagram a. What is the capacity of this system? b. If the capacity of one operation could be increased in order to increase the output of the sys- IS. tem, which operation should it be, and what amount of increase? 18 units/hr 15 units/hr 16 units/hr 3 20 units/hr 24 units/hr 8 5 6 17 units/hr 15 units/hr 17 units/hr 16. Find the capacity of this system: 22 units/hr 17 units/hr 18 units/hr 2 3 51 units/hr 54 units/hr 20 units/hr 18 units/hr 18 units/hr 5 10 8 17 units/hr 9 15 units/hr 22 units/hr
Q: Please answer, i'll leave thumbs up!!! 07. D (15) (20) (10) (10) E (30) (15) The figure above shows…
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: A process currently services an average of 55 customers per day. Observations in recent weeks show…
A: Given- Expected Demand Rate= 85% = 0.85Current service rate= 55 customers/dayCurrent Utilization =…
Q: A production line at V. J. Sugumaran's machine shophas three stations. The first station can process…
A: A Small Introduction about Bottleneck A bottleneck is a point of saturation in a supply chain (such…
Q: A small firm intends to increase the capacity of a bottleneck operation by adding a new machine. Two…
A: The Break-even point for each unit is calculated by the following formula. Ans 1: Given data for…
Q: A product line manufacturing shoes has five stations in series whose individual capacities per shift…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: Money Laundry has 22 washers and 34 dryers. All orders are first sent to wash and then to dry. It…
A: “Since you have posted a question with multiple sub-parts, we will solve the first three subparts…
Q: a. what is the relationship between design capacity, system capacity, and actual output. b. how is…
A: (a) The most frequent method of determining an organization's creative capacity necessary to meet…
Q: A. If three machines are assigned to an operator, what will be the cost per unit produced? B. If…
A: A) With the help of the data given the following points can be ascertained: Total time of work per…
Q: A production system is as shown below. Station 1 could produce 60 per hour if the rest of the line…
A: The following information is given: The system runs at a rate of 45 per hour (actual output)…
Q: a. Which machine is the constraint in this plant? Machine A Machine B v O Machine C
A: For finding the constraint amongst the three plants, the following calculations has to be done:
Q: XYZ makes two'types of products using 4 machines for 8 hours 'each day. Product A visits machines 1,…
A: Given: There are two products and using 4 machines Available time =8 hours =8*60=480 minutes
Q: Layout of an operation is concerned with O a. Uncontrollable factors O b. Flow through the operation…
A: Layout of an operation is concerned with : d. General Plant Location
Q: Charles Lackey operales a bakery in idaho Fals, idaho. Because of its excellent product and excelent…
A: Given data is Output = 1500 loaves per month Employee cost = $8 per hour Utility cost = $850…
Q: Mega Corp. is designing a product layout for a new electronic product. They plan to use this…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: A process currently services an average of 41 customers per day. Observations in recent weeks show…
A: Given data: Average customers per day = 41 Current utilisation = 90% = 0.90 The management wants a…
Q: How does capacity analysis behave when a large number of processes are operating concurrently?
A: Capacity analysis is the method involved with deciding the limit of an activity. In such manner,…
Q: a) Balance this operation using shortest operation time rule and compute the efficiency of the line.…
A: Below is the solution:-
Q: A cafeteria serving line has a coffee urn (like a system) from which customers serve them selves.…
A: 1. a) The formula for the number of customers expected on the average at the coffee is no. of…
Q: A small firm intends to increase the capacity of a bottleneck operation by adding a new machine. Two…
A: The break-even analysis helps businesses in decision-making in the following ways: Helps in…
Q: Jack, the owner and manager of Jack’s Box Company, wantsto monitor usage at Work Center 3, which is…
A: The input and output table has been completed as follows:
Q: A small firm intends to increase the capacityof a bottleneck operation by adding a new machine. Two…
A: Given data is Annual fixed costs for A = $54,000 Annual fixed costs for B = $27,000 Variable cost…
Q: Suppose a bank clears checks drawn on customers’ checking accounts by using the following process:…
A: Answer a. The capacity of the banking system is determined by the capacity of the bottleneck of the…
Q: 5 A ) A small office has 4, 4-lamp fixtures. It takes 45 minutes to clean and re-lamp the entire…
A:
Q: What is the fundamental distinction between design capacity and effective capacity? Provide a brief…
A: Capacity can be divided into two sections: Design Capacity Effective Capacity. Design Capacity…
Q: Explain why and how a firm measures process capacity
A: Process capacity is the output generated by a machine/worker under expected working conditions and…
Q: Consider a production line with five stations. Station 1 can produce a unit in 9 minutes. Station 2…
A: Given data is
Q: The manager of a car wash must decide whether to have one or two wash lines. One line will mean a…
A:
Q: A small firm intends to increase the capacity of a bottleneck operation by adding a new machine. Two…
A:
Q: Fizz Ltd. (Fizz) is a manufacturer of carbonate and soda drinks. Fizz employs approximately 100…
A: Appy Fizz is an item by Parle Agro, introduced in India in 2005. After the achievement of Appy which…
Q: a. Determine the capacity of this process. b. Which action would yield the greatest increase in…
A: Solution a) The capacity of the process is the capacity of the slowest process i.e. bottleneck. Here…
Q: egies used to
A: customer demands in McDonald's
Q: Given the following diagram, a. What is the capacity of this system? b. If the capacity of one…
A: Output of the upper leg, here, we will consider lower value= 15 units per hour, Output of the lower…
Q: A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit…
A: Given Number of machines = 2 Production capacity of machine = 4 units/hour.
Q: The following diagram describes a service process where customers go through through either of two…
A: The lowest capacity is Operation 2, which is 10 per hour when compared operation 1, 2, and 3. The…
Q: How does Goldratt’s Theory of Constraints (TOC) differ from other current approaches to continuous…
A: Difference between Theory of Constraints and Current Approaches
Q: XYZ makes two types of products using 4 machines for 8 hours each day. Product A visits machines 1,…
A:
Q: Based on the data from the below table: b. What is the system capacity in the total number of car…
A: Bottleneck process is an activity in a process which reduces the total capacity of the process. The…
Q: To meet holiday demand, Penny’s Pie Shop requires a pro-duction line that is capable of producing 50…
A: Given Information: The capacity of the shop = 50 pecan pies per week Operation hours = 40 hours per…
Q: The Morris Machine Company just received an order to refurbish five motors for materials handling…
A: Given information Time (hr) Job Workstation 1 Workstation 2 M1 12 22 M2 4 5 M3 5…
Q: Which among the following is a measure of the reserve capacity, a process has to handle in…
A: Capacity in layman's term is known as the total possible output that a firm or organization can…
Q: A manager must decide which type of machine to buy, A, B, or C. Machine costs are а. Machine Cost…
A: a) The number of machines at any annual demand can be determined using following formula: Number of…
Q: The three-station work cell illustrated in Figure S7.7has a product that must go through one of the…
A: Note: As per the Bartleby guidelines only the first three parts have been answered. The cycle time…
Q: 18. If station #2 is replaced with two parallel stations, each one performing tasks C and E what…
A: Cycle time is a proportionate time available to complete each unit of time. Here, we can identify…
Q: PLEASE PROVIDE STEPS WHEN FINDING SOLUTIONS In a SIX server model, find the percentage of the time a…
A: percentage of time a server would be busy is called server utilization. Server utilization is…
Q: 2. A manual assembly line is being planned for an assembled product whose work content time is 47.2…
A: Note- We’ll answer the first three subparts of the question since the exact one wasn’t specified.…
Q: a. An output of 930 units per shift (8.00 hours) is desired for a new processing system. The system…
A: Efficiency is the proportion between total activity time and total station time. Here, we can…
Q: What is the fundamental distinction between design capacity and effective capacity? Provide a brief…
A: Design capacity and effective capacity are two important concepts in operations management. Both of…
Q: Explain the reason why doubling the capacity of a bottleneck would not double the system capacity
A: To determine: the reason why doubling the capacity of a bottleneck would not double the system…
Can I get this explained
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- A. What is capacity? B. Why is process capacity a limiting factor in all business processes and systems? Which one isbetter: too much capacity or too little capacity? What would be the conclusi2-The process of making hotdogs involves six activities: “grind”, “mix”, “stuff”, “cook”, “peel”, and “inspect”. If the capacity of activity “cook” determines the process capacity, which of the following statements are true? a- Activity “cook” is a bottleneck activity. b- The activity time of all the other five activities is shorter than activity "cook". c- Cycle time of the process of making hotdogs is equal=1/capacity of activity “cook”. d- Increasing the capacity of activity “grind” can increase the capacity of the process of making hotdogs. All statements are correct Only statement 'b' is correct Only statements 'a' and 'b' are correct Only statements 'a', 'b' and 'c' are correct Only statement 'a' is correct Only statement 'd' is correctConsider a production line with five stations. Station 1 can produce a unit in 9 minutes. Station 2 can produce a unit in 10 minutes. Station 3 has two Identical machines, each of which can process a unit in 12 minutes (each unit only needs to be processed on one of the two machines). Station 4 can produce a unit in 5 minutes. Station 5 can produce a unit in 8 minutes. a. which station is the bottleneck station?Explain with a diagram. b. What is the capacity of the production line ? c. Compute the throughput time.
- In a job shop, effective capacity is only 88 percent of design capacity, and actual output is 69 percent of effective output. What design capacity would be needed to achieve an actual output of 11 jobs per week? What is its effective capacity?a. The Design Capacity needed to achieve the required actual job outputs =( ) (round to whole number)b. The Effective Capacity needed to achieve the required actual job outputs =( ) (round to whole number)The following diagram describes a service system where customers go through either of the two parallel three-step processes (A1-A2-A3 or B1-B2-B3) and then merge into a single line for the final step (F4). Each step has one worker assigned to it (total of 7 workers). The numbers in parentheses are the times in minutes for each step of the process. ( see attached image) What is the capacity of the entire system in terms of customers per hour? Hint: Start with calculating hourly capacity of A1-A2-A3 and B1-B2-B3. How much will the system capacity change if a second worker is assigned to step F4?A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit producedat the station needs to be processed by both of the machines.(The same unit cannot be worked on by both machines simultaneously.) Each machine has a production capacity of 4units per hour. What is the throughput time of the work cell?
- A production line at V. J. Sugumaran's machine shophas three stations. The first station can process a unit in I 0 minutes.The second station has two identical machines, each of whichcan process a unit in 12 minutes. (Each unit only needs to be processedon one of the two machines.) The third station can processa unit in 8 minutes. Which station is the bottleneck station?To meet holiday demand, Penny’s Pie Shop requires a pro-duction line that is capable of producing 50 pecan pies perweek, while operating only 40 hours per week. There areonly four steps required to produce a single pecan pie withrespective processing times of 5 minutes, 5 minutes, 45 min-utes, and 15 minutes.a. What should be the line’s cycle time?b. What is the smallest number of workstations Penny couldhope for in designing the line considering this cycletime?c. Suppose that Penny finds a solution that requires onlyfour stations. What would be the efficiency of this line?A work cell at Chris Ellis Commercial Laundry hasa workstation with two machines, and each unit produced at thestation needs to be processed by both of the machines. (The sameunit cannot be worked on by both machines simultaneously.)Each machine has a production capacity of 4 un its per hour.What is the throughput time of the work cell?
- A young mechanical engineer devised two different approaches to completing aproduction task. Both methods entail the purchase of the same working space as well asother capital equipment that will only be employed for this operation.A crew of three guys costing P30.00 per hour is required for Method A. This approachwill produce 10 units per hour, two of which will be rejects. Method B requires aworkforce of two workers, each of whom costs P35.00 per hour, to produce eight unitsper hour, one of which will be rejected. Each reject costs P20.00 because direct materialis lost. If a certain total number of units is to be produced, find which method iseconomical. DO NOT USE EXCEL, SOLVE USING FORMULAThe roller coaster at Treasure Island Amusement Park consists of 20 cars, each of which can carry up to two passengers. According to a time study, each run takes 4.5 minutes, and the time to unload and load riders is 5.5 minutes. What is the theoretical capacity of the system in number of passengers per hour? Round your answer down to the nearest whole number. _________ passengers per hourThe company has the following information about its two service departments and two production departments, Cutting and Assembly: Departments SquareFeet Number ofEmployees Maintenance Department 500 20 Cafeteria Department 1,400 10 Cutting Department 1,500 60 Assembly Department 7,100 20 What is the percentage (proportional) usage of the Maintenance Department by the Cutting Department?