Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf Club. Concrete Always enters into a contract with Dakota to construct the path for $200,000. In addition, as part of the contract, a performance bonus of $40,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,000 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 55% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 15% probability that he will be 2 weeks late. Instructions a.    Determine the transaction price that Concrete Always should compute for this agreement. b.    Assume that Jeff Heun has reviewed his work schedule and decided that it makes sense to complete this project on time. Assuming that he now believes that the probability for completing the project on time is 90% and otherwise it will be finished 1 week late, determine the transaction price.

SWFT Comprehensive Vol 2020
43rd Edition
ISBN:9780357391723
Author:Maloney
Publisher:Maloney
Chapter16: Accounting Periods And Methods
Section: Chapter Questions
Problem 41P
icon
Related questions
Question

Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf Club. Concrete Always enters into a contract with Dakota to construct the path for $200,000. In addition, as part of the contract, a performance bonus of $40,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,000 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 55% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 15% probability that he will be 2 weeks late.

Instructions

a.    Determine the transaction price that Concrete Always should compute for this agreement.

b.    Assume that Jeff Heun has reviewed his work schedule and decided that it makes sense to complete this project on time. Assuming that he now believes that the probability for completing the project on time is 90% and otherwise it will be finished 1 week late, determine the transaction price.

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Knowledge Booster
Cost management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L