Metal frames for kick scooters are manufactured in two stages: Stamping and assembly. Each frame is made up of two pieces: one part A and one part B. Currently, the stamping machine rotates its production between 120 part A’s and 120 part B’s. In the stamping machine, setup times and production rates for each part are follows:   Part A Part B Setup time (mins) 70 110 Production rate (parts per hour) 80 80 Completed parts move to assembly stage only when the entire batch is produced. At assembly, parts are assembled manually to form the finished products. The two parts and a number of small purchased components are required for each unit of final product. Each product requires 30 minutes of labor time to assemble. There are 15 workers in assembly. There is sufficient demand to sell every scooter the system can make. At the current batch size, what is the capacity of stage 1 (stamping) in [units per hour]? At the current batch size, which stage is the bottleneck of the system? Keeping everything else constant, what is the smallest batch size such that the process capacity is as large as possible?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 107P
icon
Related questions
Question

Metal frames for kick scooters are manufactured in two stages: Stamping and assembly.

Each frame is made up of two pieces: one part A and one part B. Currently, the stamping machine rotates its production between 120 part A’s and 120 part B’s.

In the stamping machine, setup times and production rates for each part are follows:

 

Part A

Part B

Setup time (mins)

70

110

Production rate (parts per hour)

80

80

Completed parts move to assembly stage only when the entire batch is produced.

At assembly, parts are assembled manually to form the finished products. The two parts and a number of small purchased components are required for each unit of final product. Each product requires 30 minutes of labor time to assemble. There are 15 workers in assembly. There is sufficient demand to sell every scooter the system can make.

  1. At the current batch size, what is the capacity of stage 1 (stamping) in [units per hour]?
  2. At the current batch size, which stage is the bottleneck of the system?
  3. Keeping everything else constant, what is the smallest batch size such that the process capacity is as large as possible?

 

 

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Optimization models
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,