of the model. A setup time of 15 minutes is also incurred per unit. a. Develop a minimum cycle to support production smoothing. What is the maximum number of cycles you can run in a shift? b. Develop an alternative minimum cycle that minimizes the number of setups within the cycle. How did the maximum number of cycles change? c. Is the ideal "one-piece-flow" possible in this example? d. Discuss the pros and cons of the solutions you developed in parts a and b.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
Please Solve In 20mins
Daily demand for three models sharing a production line are given in the table below:
Model
Daily
demand
150
100
50
The production line is run a single shift (480 minutes) per day. Processing time is 1.3 minutes per
unit, regardless of the model. A setup time of 15 minutes is also incurred per unit.
a. Develop a minimum cycle to support production smoothing. What is the maximum number of cycles
you can run in a shift?
b. Develop an alternative minimum cycle that minimizes the number of setups within the cycle. How did
the maximum numbel of cycles change?
c. Is the ideal "one-piece-flow" possible in this example?
d. Discuss the pros and cons of the solutions you developed in parts a and b.
Transcribed Image Text:Daily demand for three models sharing a production line are given in the table below: Model Daily demand 150 100 50 The production line is run a single shift (480 minutes) per day. Processing time is 1.3 minutes per unit, regardless of the model. A setup time of 15 minutes is also incurred per unit. a. Develop a minimum cycle to support production smoothing. What is the maximum number of cycles you can run in a shift? b. Develop an alternative minimum cycle that minimizes the number of setups within the cycle. How did the maximum numbel of cycles change? c. Is the ideal "one-piece-flow" possible in this example? d. Discuss the pros and cons of the solutions you developed in parts a and b.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,