Part 1: The CFO of Cruz, inc. is considering Projects A and B which are considered equally risky; the projected cash flows for the projects are shown below.    T= 0 1 2 3 4 Project A (14,500) 9,900 4,500 4,500 3000 Project B  (14,250) 5,250 5,250 5,250 7,500 1. what is the "crossover rate" for the two projects? Show the difference between the two projects' timeline in the space above. round your answer to the nearest tenth of a percent   2. Provide the NPV's for both A and B at the rates in the table below. Round to the nearest dollar/whole number.    Interest Rate  NPV project A NPV project B 0%     6%     12%     18%     24%     3. Provide the IRR for each project in the table below. show each rate to the nearest tenth of a percent. Project A IRR?  Project B IRR? 4. Calculate the MIRR for project A, and B using a WACC (discount rate). use the "combination approach" by finding the future values(show your work). Show your new time line with amounts, then find the new IRR (or MIRR) using your calculator or exel.   T= 0 1 2 3 4 Project A (14,500) 9,900 4,500 4,500 3000 Project B  (14,250) 5,250 5,250 5,250 7,500   Part 1 multiple choice 1. If each of the two Projects A and B are graphed with the interest rates shown on the horizontal axis and NPV's shown on the verical axis, which project's line would be steeper and thus more sensitive to changes in the interest rate? Hint the project that has the largest ranges of NPV outcomes in your table should be the one more sensitive to interest changes. circle answer.  A. poject a B. project b 2. assume the WACC (weighted average of cost of capital) of Cruz, inc. is 12% and the projects are mutually exclusive, which project should Cruz choose?  A. Project A only B. project B only C. Both projects D. Neither Project 3. Assuming the WACC of Cruz inc. is 20% and the projects are independent, which project should Cruz choose?  A. Project A only B. Project B only  C. Both projects D. neither project

Entrepreneurial Finance
6th Edition
ISBN:9781337635653
Author:Leach
Publisher:Leach
Chapter10: Valuing Early-stage Ventures
Section: Chapter Questions
Problem 3EP
icon
Related questions
Question

Part 1: The CFO of Cruz, inc. is considering Projects A and B which are considered equally risky; the projected cash flows for the projects are shown below. 

 

T=

0

1

2

3

4

Project A

(14,500)

9,900

4,500

4,500

3000

Project B 

(14,250)

5,250

5,250

5,250

7,500

1. what is the "crossover rate" for the two projects? Show the difference between the two projects' timeline in the space above. round your answer to the nearest tenth of a percent

 

2. Provide the NPV's for both A and B at the rates in the table below. Round to the nearest dollar/whole number. 

 

Interest Rate 

NPV project A

NPV project B

0%

   

6%

   

12%

   

18%

   

24%

   

3. Provide the IRR for each project in the table below. show each rate to the nearest tenth of a percent.

Project A IRR? 

Project B IRR?

4. Calculate the MIRR for project A, and B using a WACC (discount rate). use the "combination approach" by finding the future values(show your work). Show your new time line with amounts, then find the new IRR (or MIRR) using your calculator or exel.

 

T=

0

1

2

3

4

Project A

(14,500)

9,900

4,500

4,500

3000

Project B 

(14,250)

5,250

5,250

5,250

7,500

 

Part 1 multiple choice

1. If each of the two Projects A and B are graphed with the interest rates shown on the horizontal axis and NPV's shown on the verical axis, which project's line would be steeper and thus more sensitive to changes in the interest rate? Hint the project that has the largest ranges of NPV outcomes in your table should be the one more sensitive to interest changes. circle answer. 

A. poject a

B. project b

2. assume the WACC (weighted average of cost of capital) of Cruz, inc. is 12% and the projects are mutually exclusive, which project should Cruz choose? 

A. Project A only

B. project B only

C. Both projects

D. Neither Project

3. Assuming the WACC of Cruz inc. is 20% and the projects are independent, which project should Cruz choose? 

A. Project A only

B. Project B only 

C. Both projects

D. neither project

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Entrepreneurial Finance
Entrepreneurial Finance
Finance
ISBN:
9781337635653
Author:
Leach
Publisher:
Cengage
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
International Financial Management
International Financial Management
Finance
ISBN:
9780357130698
Author:
Madura
Publisher:
Cengage
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College