Q5. The details regarding Labour force engaged in a work scheduled to be completed in 30 hours are as follows-                                                                                                      Category of Workers Standard Number Standard wage rate/hr. (in Rs.) Actual Number Actual Wage rate/hr. (in Rs.) Skilled 75 60 70 70 Semi-Skilled 45 40 30 50 Un Skilled 60 30 80 20 Total 180   180   The work is actually completed in 32 hours. Calculate Labour Variances. Show your working clearly.

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter8: Standard Costs And Variances
Section: Chapter Questions
Problem 7PA: Ellis Companys labor information for September is as follows: A. Compute the standard direct labor...
icon
Related questions
Topic Video
Question

Q5. The details regarding Labour force engaged in a work scheduled to be completed in 30 hours are as follows-                                                                                                     

Category of Workers

Standard Number

Standard wage rate/hr. (in Rs.)

Actual Number

Actual Wage rate/hr. (in Rs.)

Skilled

75

60

70

70

Semi-Skilled

45

40

30

50

Un Skilled

60

30

80

20

Total

180

 

180

 

The work is actually completed in 32 hours. Calculate Labour Variances. Show your working clearly.

Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College