Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The​ activities, immediate​ predecessors, and times appear in the accompanying​ table:                                                                                       Activity Immediate​ Predecessor(s) Time​ (days) A ------ 3 B ------ 7 C ------ 1 D B 10 E ​A, D 5 F C 5 G ​E, F 10 Calculate the slack time for A.

MARKETING 2018
19th Edition
ISBN:9780357033753
Author:Pride
Publisher:Pride
Chapter6: Target Markets: Segmentation And Evaluation
Section: Chapter Questions
Problem 4SC
icon
Related questions
Question
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The​ activities, immediate​ predecessors, and times appear in the accompanying​ table:
                                                                                     
Activity
Immediate​ Predecessor(s)
Time​ (days)
A
------
3
B
------
7
C
------
1
D
B
10
E
​A, D
5
F
C
5
G
​E, F
10

Calculate the slack time for A.

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Knowledge Booster
Outsourcing
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L