Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A ------ 3 B ------ 7 C ------ 1 D B 10 E A, D 5 F C 5 G E, F 10 Calculate the slack time for A.
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A ------ 3 B ------ 7 C ------ 1 D B 10 E A, D 5 F C 5 G E, F 10 Calculate the slack time for A.
Chapter6: Target Markets: Segmentation And Evaluation
Section: Chapter Questions
Problem 4SC
Related questions
Question
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity
|
Immediate Predecessor(s)
|
Time (days)
|
A
|
------ |
3
|
B
|
------ |
7
|
C
|
------ |
1
|
D
|
B
|
10
|
E
|
A, D
|
5
|
F
|
C
|
5
|
G
|
E, F
|
10
|
Calculate the slack time for A.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 3 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Recommended textbooks for you