Sometimes, in an effort to control project schedule, it is possible that a project manager may resort to developing a project schedule by starting at the end of a project end date and working back toward the beginning. In doing that, the project manager may attempt to identify and estimate the activities' duration that would eventually add up to the amount of time that the project is estimated to take. While this may seem like a reasonable approach to developing a project schedule, it is possible that using this strategy may substantially decrease the chances that the project will meet its schedule. Do you think this approach to developing a project schedule is the right one to use? Discuss the rationale for your answer. Discuss the reasons why this approach could substantially decrease the chances of the project meeting its schedule.

Question

Sometimes, in an effort to control project schedule, it is possible that a project manager may resort to developing a project schedule by starting at the end of a project end date and working back toward the beginning. In doing that, the project manager may attempt to identify and estimate the activities' duration that would eventually add up to the amount of time that the project is estimated to take. While this may seem like a reasonable approach to developing a project schedule, it is possible that using this strategy may substantially decrease the chances that the project will meet its schedule. Do you think this approach to developing a project schedule is the right one to use? Discuss the rationale for your answer. Discuss the reasons why this approach could substantially decrease the chances of the project meeting its schedule.

check_circleAnswer
Step 1

When the planning is done by doing a backward sweep on the project plan, then all the activities start and finish timings are the...

Want to see the full answer?

See Solution

Check out a sample Q&A here.

Want to see this answer and more?

Our solutions are written by experts, many with advanced degrees, and available 24/7

See Solution
Tagged in

Business

Operations Management

Program evaluation and review technique

Related Operations Management Q&A

Find answers to questions asked by student like you

Show more Q&A add
question_answer

Q: 10

A: The option (c ) represents the correct graphical solution. As the feasible area is bound by the firs...

question_answer

Q: I need a detailed explanation and assistance to solve this problem: Wineco produces wine cooler as a...

A: Since the model is needed to solve for the quantities of ingredients to be purchased in order to max...

question_answer

Q: Many organizations establish project management office (PMO) as an integral part of their organizati...

A: Requirement for PMOLarge software development projects especially where the product is going to be u...

question_answer

Q: What are the different approaches to research, and what are the differences between them

A: The different approaches of research are quantitative and qualitative research. Both quantitative an...

question_answer

Q: What you need to be a successful student?

A: The following are the qualities or skills needed to be a successful student:Studies must be the firs...

question_answer

Q: you are asked to develop an experiment for​ a study of the effect that has on the response rates sec...

A: According to the given scenario there are different types of complex experimental design including f...

question_answer

Q: characteristics of good managers?

A: Characteristics of good managers:Apart from the name of position of manager it is very critical for ...

question_answer

Q: document key factors a production manager needs to consider when scheduling production in the organi...

A: Key factors a production manager needs to consider when scheduling production in the organization:(1...

question_answer

Q: 34

A: Since the expected duration is 65 days and the S.D. is 9 days, hence if the value of 80 days is (80 ...

Sorry about that. What wasn’t helpful?