Table 3 shows the process sequence in a production line and its related direct time study data. The production process must follow a specific route of processes A, B, C, and D respectively. Task A is in full automatic mode and requires one operator at the workstation. The worker at task B was rated with 90%, the worker at task C was rated with 115% and the worker at task D was rated with 80%. The standard allowances accepted by the company are 6% for fatigue, 5% for personal, and 4% for delay. The normal operating period is 8 hours per day and 24 days per month. Analyse the given information and determine the standard time for the product in minutes. Table 3: Average Processing Time (minutes) Job Description Average Processing Time A Automatic B Manual 40 C Manual 30 Manual 35

Precision Machining Technology (MindTap Course List)
2nd Edition
ISBN:9781285444543
Author:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Chapter2: Measurement, Materials, And Safety
Section2.5: Quality Assurance, Process Planning, And Quality Control
Problem 10RQ: If an X-bar chart graph falls below the LCL or rises above the UCL, a machining process is said to...
icon
Related questions
Question
Table 3 shows the process sequence in a production line and its related direct
time study data. The production process must follow a specific route of
processes A, B, C, and D respectively. Task A is in full automatic mode and
requires one operator at the workstation. The worker at task B was rated with
90%, the worker at task C was rated with 115% and the worker at task D was
rated with 80%. The standard allowances accepted by the company are 6% for
fatigue, 5% for personal, and 4% for delay. The normal operating period is 8
hours per day and 24 days per month. Analyse the given information and
determine the standard time for the product in minutes.
Table 3: Average Processing Time (minutes)
Job
Description
Average
Processing Time
A
Automatic
B
Manual
40
C
Manual
30
D
Manual
35
Transcribed Image Text:Table 3 shows the process sequence in a production line and its related direct time study data. The production process must follow a specific route of processes A, B, C, and D respectively. Task A is in full automatic mode and requires one operator at the workstation. The worker at task B was rated with 90%, the worker at task C was rated with 115% and the worker at task D was rated with 80%. The standard allowances accepted by the company are 6% for fatigue, 5% for personal, and 4% for delay. The normal operating period is 8 hours per day and 24 days per month. Analyse the given information and determine the standard time for the product in minutes. Table 3: Average Processing Time (minutes) Job Description Average Processing Time A Automatic B Manual 40 C Manual 30 D Manual 35
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Project Management Techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Precision Machining Technology (MindTap Course Li…
Precision Machining Technology (MindTap Course Li…
Mechanical Engineering
ISBN:
9781285444543
Author:
Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:
Cengage Learning