
FINANCIAL ACCOUNTING
10th Edition
ISBN: 9781259964947
Author: Libby
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Tamra, Inc. began work on a $ 7000,000 contract in 2019 to construct an office building. During 2010, Tamra, Inc. incurred costs of $1,700,00, billed their customers for $1,200,000, and collected $960,000. At December 31,2019, the estimated future costs to complete the project total $3,300,000.
Instructions: compute Tamra’s Gross profit to be recognized in 2019?
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Curtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod Associates on July 1, 2024, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The building was completed on December 31, 2026. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date At 12-31-2024 At 12-31-2025 $367,000 3,303,000 728,000 $ 2,856,000 1,904,000 2,330,000 Ren 1 and 2 10% Dan 3 60% Answer is not complete. Complete this question by entering your answers in the tabs below. Required: 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three…arrow_forwardBuild a Bridge Inc. prepares its financial statements in accordance with IFRS. The company started work on a contract in May 2023 to build a small bridge at a fixed price of $10,000,000. The bridge was to be completed by September 2025 at a total estimated cost of $8,000,000. Total cumulative costs incurred by the end of December 2023 and 2024 were $2,000,000 and $5,500,000, respectively. Because of cost overruns in 2024, it is now expected that the project will cost $800,000 more than originally estimated. Final costs at the end of the project totalled $9,000,000. Required Determine the amount of gross profit to be recognized for the years ending December 31, 2023 and 2024. First calculate the percent complete on December 31, 2023. The percent complete on December 31, 2023 is %.arrow_forwardIndiana Co. began a construction project in 2018 with a contract price of $162 million to be received when the project is completed in 2020. During 2018, Indiana incurred $33 million of costs and estimates an additional $85 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2019, Indiana incurred additional costs of $64 million and estimated an additional $51 million in costs to complete the project. Indiana (Do not round your percentage calculated): Multiple Choice Recognized $3.00 million loss on the project in 2019. Recognized $6.13 million gross profit on the project in 2019. Recognized $3.13 million loss on the project in 2019. Recognized $3.13 million gross profit on the project in 2019.arrow_forward
- Cullumber Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.6 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Costs to date $816,000 $1,664,400 $2,182,000 Estimated costs to complete 1,584,000 525,600 0 Progress billings to date (non-refundable) 860,000 2,132,000 2,600,000 Cash collected to date 716,000 2,023,000 2,600,000 Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) 2020 Gross profit/(loss) $ 2021 2022arrow_forwardIn 2021, the Kokosing Construction Company of Columbus, Ohio entered into a contract to construct a road for Franklin County for $20,000,000. The road was completed in 2023. Information pertaining to the contract is provided below: 2021 2022 2023 Costs incurred during the year Estimated costs to complete as of year end Billings during the year Cash Collections during the year $4,800,000 $7,200,000 $4,400,000 11,200,000 4,000,000 4,000,000 8,000,000 8,000,000 3,600,000 7,200,000 9,200,000 Kokosing recognizes revenue over time according to percentage of completion. Required: 1. Compute the amount of revenue and gross profit to be recognized in 2021, 2022, and 2023. 2. Prepare the necessary journal entries for 2021 and 2022. Use the following accounts for your journal entries - "Construction in Progress", "Cash, Materials etc.", "Accounts Receivable", "Billings on Construction in Progress", "Cash", "Cost of Construction", and "Revenue from Long-term contracts". 3. Prepare a partial…arrow_forwardCurtiss Construction Company, Incorporated, entered into a fixed price contract with Axelrod Associates on July 1, 2024, to construct a four story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000 The building was completed on December 31, 2026 Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows Percentage of completion Cests incurred to date Estimated costs to complete Billings to Axelrod, to date Required: At 12-11-2024 10% At 12-31-2025 $2,688,000 1,792,000 AT 12-11-2026 60% 100% $ 4,534,000 4,240,000 $363,000 3,267,000 724,000 2,250,000 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue…arrow_forward
- Domesticarrow_forwardGarnet Corporation enters into a 4-year construction contract worth $100 million with Gold company on January 1, 2022. At the end of 2022, construction costs totaled $20 million and Garnet estimates $60 million of construction costs remain. If Garnet uses the percent of completion method to determine revenues, how much revenue will Garnet recognize in 2022 related to the construction contract?arrow_forwardIn 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,344,000 $ 3,960,000 $ 1,645,600 Estimated costs to complete as of year-end 5,456,000 1,496,000 0 Billings during the year 2,800,000 4,504,000 2,696,000 Cash collections during the year 2,600,000 4,400,000 3,000,000 Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.Required:1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).2-b. In the journal below, complete the necessary journal entries…arrow_forward
- What is the answer and how do you get the answer? Dixon Development began operations in December 2021. When lots for industrial development are sold, Dixon recognizes income for financial reporting purposes in the year of the sale. For some lots, Dixon recognizes income for tax purposes when collected. Income recognized for financial reporting purposes in 2021 for lots sold this way was $15 million, which will be collected over the next three years. Scheduled collections for 2022–2024 are as follows: 2022 $ 5 million 2023 7 million 2024 3 million $ 15 million Pretax accounting income for 2021 was $20 million. The enacted tax rate is 30%. Required:1. Assuming no differences between accounting income and taxable income other than those described above, prepare the journal entry to record income taxes in 2021.2. Suppose a new tax law, revising the tax rate from 30% to 25%, beginning in 2023, is enacted in 2022, when pretax accounting income was $17…arrow_forwardSuppose a company spends $100,000 on research and development in 2021. As a result of the products developed, additional revenue is generated over the next five years totaling $600,000. When is the cost of the research and development in 2021 recognized as an expense? Multiple Choice Evenly over the period 2022-2026. Full amount in 2026. Evenly over the period 2021-2025. Full amount in 2021.arrow_forwardOn February 1, 2023, Sandhill Contractors agreed to construct a building at a contract price of $3,460,000. The total estimated construction costs would be $1,890,000 and the project would be finished in 2025. Information relating to the costs and billings for this contract is as follows: Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date 2023 Gross profit/ (loss) 689,850 1,200,150 1,100,000 1,000,000 2023 2024 573050 $1,162,000 $ 2,365,000 913,000 1,890,000 1,750,000 2025 Calculate the gross profit / (loss) that should be recognized for 2023, 2024, and 2025 using the percentage completion method. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round percentage complete to 1 decimal place, e.g. 15.2% and final answers to O decimal places, e.g. 5,125.) 2024 -0- 3,460,000 2,950,000 -107450 $ LA 2025 40450arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education


Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON

Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education