Use the following information to answer the next question. Quantity 100 pieces Cycle Time per Piece Hours) Queue (Days) Set-Up (Hours) 10 Saw 20 Face 30 Turn 40 Drill 2 2 2 5 .5 2 2 50 Grind 2 A one-shift operation, 8 hours/day with 100 % efficiency should be assumed. 43. If the order in the job shop described above starts on the beginning of day 1, when would it be finished? A. Day 20 B. Day 23 C. Day 28 D. Day 30

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
100%
Use the following information to answer the next question.
Quantity 100 pieces
Cycle Time
per Piece
Hours)
Queue
(Days)
Set-Up
(Hours)
10 Saw
20 Face
30 Turn
40 Drill
2
2
2
5
.5
2
2
50 Grind
2
A one-shift operation, 8 hours/day with 100 % efficiency should be assumed.
43. If the order in the job shop described above starts on the beginning of day 1, when would it be
finished?
A. Day 20
B. Day 23
C. Day 28
D. Day 30
Transcribed Image Text:Use the following information to answer the next question. Quantity 100 pieces Cycle Time per Piece Hours) Queue (Days) Set-Up (Hours) 10 Saw 20 Face 30 Turn 40 Drill 2 2 2 5 .5 2 2 50 Grind 2 A one-shift operation, 8 hours/day with 100 % efficiency should be assumed. 43. If the order in the job shop described above starts on the beginning of day 1, when would it be finished? A. Day 20 B. Day 23 C. Day 28 D. Day 30
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,