Production and Operations Analysis, Seventh Edition
Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 10, Problem 26AP

A.

Summary Introduction

Interpretation: A network diagram representing the activities of the project is to be constructed.

Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.

A.

Expert Solution
Check Mark

Explanation of Solution

Given information: Theactivities to be taken up for the construction of a gas station and the time duration for each are given in the table.

    ActivityTime
    A4
    B2
    C3
    D1
    E1
    F2
    G3
    H1
    I5
    J3
    K4
    L2
    M1

The activity times and the precedence relationship are shown in the table:

    ActivityTimePredecessors
    A4 
    B2A
    C3B
    D1C
    E1D
    F2B
    G3F
    H1G
    I5B
    J3I
    K4C, F, I
    L2K
    M1L

The network diagram showing the work flows is as follows:

  Production and Operations Analysis, Seventh Edition, Chapter 10, Problem 26AP , additional homework tip  1

B.

Summary Introduction

Interpretation: The critical path is to be identified by computing the earliest and the latest start and finish times.

Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.

B.

Expert Solution
Check Mark

Answer to Problem 26AP

The critical path is A − B − I − K − L − M with completion time as 18 weeks

Explanation of Solution

Given information:

    ActivityTime
    A4
    B2
    C3
    D1
    E1
    F2
    G3
    H1
    I5
    J3
    K4
    L2
    M1

  Production and Operations Analysis, Seventh Edition, Chapter 10, Problem 26AP , additional homework tip  2

The earliest and latest start and finish times are calculated using the formulae:

Earliest Start (EST) = Maximum EFT of the predecessor activity

Latest Start (LST) = LFT - Duration

Earliest Finish (EFT) = EST + Duration

Latest Finish (LFT) = Minimum LST of the immediate successor

Slack = LFT − EFT (or) LST − EST

    ActivityTimeESTEFTLSTLFTSlack
    A404040
    B246460
    C3698112
    D191016177
    E1101117187
    F2689113
    G381114176
    H1111217186
    I56116110
    J3111415184
    K4111511150
    L2151715170
    M1171817180

The critical path includes the activities with zero slack. So, here the critical path is A − B− I − K − L − M. The total time taken to complete the project is 18 weeks.

C.

Summary Introduction

Interpretation: A Gantt chart of the schedule for the project is to be drawn.

Concept Introduction: Gantt chart is a project management tool that is a type of bar chart. It depicts the project schedule and is used for resource allocation.

C.

Expert Solution
Check Mark

Answer to Problem 26AP

A Gantt chart for the project has been drawn.

Explanation of Solution

Given information:

    ActivityTime
    A4
    B2
    C3
    D1
    E1
    F2
    G3
    H1
    I5
    J3
    K4
    L2
    M1

Activity times and early start times:

    ActivityESTTime
    A04
    B42
    C63
    D91
    E101
    F62
    G83
    H111
    I65
    J113
    K114
    L152
    M171

The Gantt chart depicting the project based on the EST:

  Production and Operations Analysis, Seventh Edition, Chapter 10, Problem 26AP , additional homework tip  3

D.

Summary Introduction

Interpretation: The impact of replacement of the air compressor which takes two weeks on the completion of the project is to be determined.

Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.

D.

Expert Solution
Check Mark

Explanation of Solution

Given information:

    ActivityTime
    A4
    B2
    C3
    D1
    E1
    F2
    G3
    H1
    I5
    J3
    K4
    L2
    M1

Installing the air compressor is represented by activity G.

    ActivityTimeESTEFTLSTLFTSlack
    A404040
    B246460
    C3698112
    D191016177
    E1101117187
    F2689113
    G381114176
    H1111217186
    I56116110
    J3111415184
    K4111511150
    L2151715170
    M1171817180

The latest start time of the activity G is 14th week. If the failure is identified before installation, the project will not be delayed as the replacement time (2 weeks) is less than the slack (6 weeks).

If the failure is found during testing of the air compressor, represented by activity H, still the project would not be delayed, as again there is a slack of 6 weeks.

E.

Summary Introduction

Interpretation: The activities that can be completed by the end of the 15th week without delaying the project completion are to be determined.

Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.

E.

Expert Solution
Check Mark

Answer to Problem 26AP

The activities A, B, C, F and I have to be completed by the end of the 15th week to guarantee project completion without delay.

Explanation of Solution

Given information:

    ActivityTime
    A4
    B2
    C3
    D1
    E1
    F2
    G3
    H1
    I5
    J3
    K4
    L2
    M1

The table shows the Earliest and Latest times of the activities

    ActivityTimeESTEFTLSTLFTSlack
    A404040
    B246460
    C3698112
    D191016177
    E1101117187
    F2689113
    G381114176
    H1111217186
    I56116110
    J3111415184
    K4111511150
    L2151715170
    M1171817180

The latest finish times of the activities A, B, C, F and Iam less than 15 weeks. Therefore, these activities have to be completed by the end of the 15th weeks to guarantee project completion without any delay.

F.

Summary Introduction

Interpretation: The optimal solution for the problem is to be determined using linear programming.

Concept Introduction: Linear programming is a mathematical technique used to achieve the best outcome, given a list of parameters usually restrictions on the resources.

F.

Expert Solution
Check Mark

Answer to Problem 26AP

The optimal solution for the problem is obtained using linear programming.

Explanation of Solution

Given information:

    ActivityTime
    A4
    B2
    C3
    D1
    E1
    F2
    G3
    H1
    I5
    J3
    K4
    L2
    M1

The various paths of the project and the durations are:

  Production and Operations Analysis, Seventh Edition, Chapter 10, Problem 26AP , additional homework tip  4

The critical path is A − B − I − K − L − M with the completion time of 18 weeks.

Using linear programming, the EST is calculated.

Objective function = =SUM (B2:M2)

    Nodes123456789101112
    EST            

The constraints

    Activity  Time
    A0>4
    B0>2
    C0>3
    D0>1
    E0>1
    F0>2
    G0>3
    H0>1
    I0>5
    J0>3
    K0>4
    L0>2
    M0>1
    P10>0
    P20>0
    P30>0

Solver Solution:

    Objective Function
    120

EST for the nodes:

    Nodes123456789101112
    EST0469811111110151718

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The Lotus Point Condo Project will contain both homes and apartments. The site can accommodate up to 10,000 dwelling units. The project must contain a recreation project: either a swimming-tennis complex or a sailboat marina, but not both. If a marina is built, then the number of homes in the project must be at least triple the number of apartments in the project. A marina will cost $1.2 million, and a swimming-tennis complex will cost $2.8 million. The developers believe that each apartment will yield revenues with a net present value of $48,000, and each home will yield revenues with a net present value of $46,000. Each home (or apartment) costs $40,000 to build. Formulate an integer program to help Lotus Point maximize profits.
Monica and Isabel are roommates who, on this particular Saturday morning, are trying to decide what scarf to wear. Each has a Burberry scarf (which we’ll denote B), a tan scarf (denoted T), and a mauve scarf (denoted M). They care about the scarf but also about whether they end up wearing the same or different scarves. The preference ordering (from best to least preferred outcome) for Monica is: (1) she wears B and Isabel wears T or M; (2) she wears T and Isabel wears B or M; (3) she wears B and Isabel wears B; (4) she wears T and Isabel wears T: (5) she wears M and Isabel wears M; and (6) she wears M and Isabel wears B or T. Isabel’s preference ordering is: (1) she wears T and Monica wears B or M; (2) she wears M and Monica wears B or T; (3) she wears T and Monica wears T; (4) she wears M and Monica wears M; (5) she wears B and Monica wears B; and (6) she wears B and Monica wears T or M. Applying the IDSDS, which scarves will be worn?
A project faces uncertainty about the number of users of the service to be provided. It might be 10, 20, or 40 with probabilities 0.3, 0.5, and 0.2, respectively. There are two options, A and B. Under option A, the value per user is $10. Under option B, the value per user is $5 with probability 0.4 and otherwise $20. Assume the number of users and the value per user under option A are independent. Option A costs $100 and option B costs $250. a. Set up the table b. What are the expected values for each option? c. What is the value of perfect information before the decision is made? d. Suppose the decision maker could, for a price, determine whether value per user would be 5 or 20 under option B, tough you would learn nothing about the number of users. What is the value of that information?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY