1.

To determine

Calculate the velocity and theoretical cycle time that takes to produce one model

1.

Expert Solution
Check Mark

Explanation of Solution

Cycle time: Cycle time and velocity are two operational “measures of responsiveness”. Cycle time is the span of time taken to produce a unit of output from the time the materials are received till the good is supplied to finished goods inventory. Therefore, cycle time is the time taken to produce a product.

Velocity: Velocity is the number of units of output that can be produced within a given period of time.

Calculate the theoretical velocity:

Theoreticalvelocity=TheoreticaloutputCelltime=27,900models37,200hours=0.75modelperhour

Calculate theoretical cycle time:

Theoreticalcycletime=TimetakenModelsproducedperhour=60minutes0.75modelperhour=80minutespermodel

2.

To determine

Calculate the actual velocity and the actual cycle time.

2.

Expert Solution
Check Mark

Explanation of Solution

Calculate the actual velocity:

Actualvelocity=ActualoutputActualcelltime=23,250models37,200hours=0.625modelperhour

Calculate actual cycle time:

Actualcycletime=TimetakenModelsproducedperhour=60minutes0.625modelperhour=96minutespermodel

3.

To determine

Calculate the manufacturing efficiency cycle and comment on the efficiency of the operation.

3.

Expert Solution
Check Mark

Explanation of Solution

Manufacturing efficiency ratio: Manufacturing efficiency ratio is a measure of Just-In-Time (JIT) manufacturing system and it expresses the time spent in value-added activities as a percentage of total cycle time.

Calculate Manufacturing cycle efficiency:

Manufacturingcycleefficiency}=TheoreticaltimeActualtime=80minutespermodel96minutespermodel=0.83

Therefore, from the above calculation, it is noted that, the “efficiency of the operation” is very high.

4.

To determine

Compute the budgeted conversion cost per minute, compute the conversion cost per model, compute the conversion cost per model for actual output and explain whether the product costing approach provide an incentive for the cell manager to reduce cycle time.

4.

Expert Solution
Check Mark

Explanation of Solution

Calculate budgeted conversion cost:

Budgetedconversioncostperminute=Budgetedconversioncost(Celltime×Timetaken)=$6,696,00037,200hours×60minutes=$6,696,0002,232,000minutes=$3perminute

Calculate theoretical conversion cost per model:

Theoretical conversioncost per model}=Budgetedconversioncost×Theoreticalcycletime=$3×80minutespermodel=$240 permodel

Calculate actual conversion cost per model:

Actualconversioncostpermodel}=Budgetedconversioncost×Actualcycletime=$3×96minutespermodel=$288permodel

Yes, the cost per unit can be decreased by decreasing cycle time. The potential reduction is $48 (1) per model.

Working note:

(1)Calculate the potential reduction:

Potentialreduction=(ActualconversioncostpermodelTheoreticalconversioncostpermodel)=$288$240=$48permodel

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Golding Manufacturing, a division of Farnsworth Sporting, Inc., produces two different models of bows and eight models of knives. The bow-manufacturing process involves the production of two major subassemblies: the limbs and the handle. The limbs pass through four sequential processes before reaching final assembly: lay-up, molding, fabricating, and finishing. In the Lay-Up Department, limbs are created by laminating layers of wood. In Molding, the limbs are heat treated, under pressure, to form a strong resilient limb. In the Fabricating Department, any protruding glue or other processing residue is removed. Finally, in Finishing, the limbs are cleaned with acetone, dried, and sprayed with the final finishes. The handles pass through two processes before reaching final assembly: pattern and finishing. In the Pattern Department, blocks of wood are fed into a machine that is set to shape the handles. Different patterns are possible, depending on the machine's setting. After coming out…
iSounds Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed, the operator moves the assembled boards to the final assembly area. This move takes 9 minutes to complete. The final assembly for each stereo unit requires 21 minutes and is also done in batches of 50 units. A batch of 50 stereos is moved into the test building, which is across the street. The move takes 20 minutes. Before conducting the test, the test equipment must be set up for the particular stereo model. The test setup requires 30 minutes. The…
Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed, the operator moves the assembled boards to the final assembly area. This move takes 12 minutes to complete. The final assembly for each stereo unit requires 19 minutes and is also done in batches of 50 units. A batch of 50 stereos is moved into the test building, which is across the street. The move takes 20 minutes. Before conducting the test, the test equipment must be set up for the particular stereo model. The test setup requires 30 minutes. The…

Chapter 13 Solutions

Cornerstones of Cost Management (Cornerstones Series)

Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning