Redo Problem 18.10 using the λ method for estimating the skin resistance.
18.10 A concrete pile 15 m long with a cross section of 380 mm × 380 mm is fully embedded in a saturated clay layer. For the clay, γsat = 18 kN/m3, ϕ = 0, and cu = 80 kN/m2. Assume that the water table lies below the tip of the pile. Determine the allowable load that the pile can carry (FS = 3). Use the a method to estimate the skin resistance.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider a 13.5 m long concrete pile with a diameter of 0.45 m fully embedded
in sand. For the sand, given unit weight, ? = 17.5 kN/m3
; and soil friction angle,
ϕ’ = 36
o
. Estimate the frictional resistance according to Coyle and Castello’s
method.
The wooden pile shown in the figure has a diameter of 95 mm and is subjected to a load of P = 80 kN. Along the length of the pile and around its perimeter, soil supplies a constant frictional resistance of w = 2.90 kN/m. The length of the pile is L = 5.6 m and its elastic modulus is E = 8.6 GPa.Calculate(a) the force FB needed at the base of the pile for equilibrium.(b) the magnitude of the downward displacement at A relative to B.
The wooden pile shown in the figure has a diameter of 95 mm and is subjected to a load of P = 80 kN. Along the length of the pile and around its perimeter, soil supplies a constant frictional resistance of w = 4.82 kN/m. The length of the pile is L = 4.0 m and its elastic modulus is E = 10.4 GPa.
Calculate
(a) the force FB needed at the base of the pile for equilibrium.
(b) the magnitude of the downward displacement at A relative to B.
Chapter 18 Solutions
Fundamentals of Geotechnical Engineering (MindTap Course List)
Ch. 18 - State whether the following are true or false. a....Ch. 18 - A 1500 kN load was applied on two 20 m long and...Ch. 18 - A 500 mm diameter and 20 m long concrete pile is...Ch. 18 - A 400-mm diameter and 15 m long concrete pile is...Ch. 18 - A 400 mm 400 mm square precast concrete pile of...Ch. 18 - Prob. 18.6PCh. 18 - Prob. 18.7PCh. 18 - Prob. 18.8PCh. 18 - Determine the maximum load that can be allowed on...Ch. 18 - Prob. 18.10P
Ch. 18 - Redo Problem 18.10 using the method for...Ch. 18 - Determine the maximum load that can be allowed on...Ch. 18 - Prob. 18.13PCh. 18 - A steel pile (H-section; HP 360 1.491; see Table...Ch. 18 - A concrete pile is 18 m long and has a cross...Ch. 18 - Prob. 18.16PCh. 18 - Prob. 18.17PCh. 18 - Prob. 18.18PCh. 18 - Prob. 18.19PCh. 18 - Figure 18.26a shows a pile. Let L = 20 m, D = 450...Ch. 18 - Refer to Figure 18.26b. Let L = 15.24 m, fill =...Ch. 18 - Prob. 18.22PCh. 18 - Figure 18.39 shows a 3 5 pile group consisting of...Ch. 18 - The section of a 4 4 group pile in a layered...Ch. 18 - Prob. 18.25PCh. 18 - Prob. 18.26CTP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- Refer to Figure 18.26b. Let L = 15.24 m, fill = 17.29 kN/m3, sat(clay) = 19.49 kN/m3, clay = 20, Hf = 3.05 m, and D = 0.406 m. The water table coincides with the top of the clay layer. Determine the total downward drag on the pile. Assume that = 0.6 clay. FIG. 18.26 Negative skin frictionarrow_forwardA 600 mm diameter and 25 m long driven concrete pile carries a column load of 1200 kN. It is estimated that the shaft carries 900 kN and the point carries 300 kN. Determine the settlement of the pile head using the Poulos and Davis method with the following data: Es = 25 MN/m2, Ep = 30,000 MN/m2, and s = 0.2arrow_forwardRefer to Figure 18.9. A cantilever sheet pile is driven into a granular soil where the water table is 2 m (L1) below the top of the sand. The properties of the sand are =40, =17.5kN/m3, and sat=19kN/m3. It is proposed to excavate to a depth of 6 m (L) below the ground level. Determine the actual depth to which the sheet pile must be driven (L + D), using the net lateral pressure diagram. Note: Dactual=1.3(L3+L4)theoryarrow_forward
- A 600 mm diameter and 25 m long driven concrete pile carries a column load of 1200 kN. It is estimated that the shaft carries 900 kN and the point carries 300 kN. Determine the settlement of the pile head using the Poulos and Davis method with the following data: Es = 25 MN/m2, Ep = 30,000 MN/m2 and ?s = 0.2.arrow_forwardThe section of a 4 x 4 group pile in a layered saturated clay is shown in Figure P 9.29. The piles are square in cross section (356 mm x 356 mm). The center-to-center spacing (d) of the piles is 1 m. Determine the allowable load bearing capacity of the pile group. Use FS = 3 and Table 9.10.arrow_forwardConsider a 15 m long concrete pile with a cross section of 0.45 m x 0.45 m fully embedded in sand.For the sand, unit weight, γ = 17 kN/m3 and soil friction angle, ϕ’ = 35o. Estimate the ultimate point??? with each of the following:1.1 Meyerhof’s method (Ans: 1014 kN)1.2 Vesic’s method (Ans: 1754 kN)1.3 Coyle and Castello’s method (Ans: 2479 kN)arrow_forward
- The plan of a group pile is shown in the figure. Assume that the piles areembedded in a saturated homogeneous clay having a cu=90 kN/m2 . Given: Diameter of piles (D)=316 mm, center-to-center spacing of piles=600 mm, and length of piles= 20 m. Find the allowable load-carrying capacity of the pile group. Using FS=3 and table.arrow_forwardIn Problem 18.4, find the maximum bending moment in the sheet pile and determine the required section modulus, assuming an allowable stress of 190 MN/m2. 18.4 Refer to Figure 18.13. Given L1 = 1.5 m, L2 = 3 m; for the sand, =33, =16.5kN/m3, sat=19.0kN/m3; and, for the clay, c=50kN/m2, =0, sat=20kN/m3. Determine the depth of sheet pile required, allowing for a 50% increase from the theoretical estimate.arrow_forwardRedo Problem 12.20 using Vesics method, assuming that the skin friction is distributed uniformly along the shaft. 12.20 A 600 mm diameter and 25 m long driven concrete pile carries a column load of 1200 kN. It is estimated that the shaft carries 900 kN and the point carries 300 kN. Determine the settlement of the pile head using the Poulos and Davis method with the following data: Es = 25 MN/m2, Ep = 30,000 MN/m2, and s = 0.2arrow_forward
- Refer to Figure 18.13. Given L1 = 1.5 m, L2 = 3 m; for the sand, =33, =16.5kN/m3, sat=19.0kN/m3; and, for the clay, c=50kN/m2, =0, sat=20kN/m3. Determine the depth of sheet pile required, allowing for a 50% increase from the theoretical estimate.arrow_forwardRedo Problem 12.30 assuming that the water table coincides with the top of the fill and that sat(fill) = 19.8 kN/m3. If the other quantities remain the same, what would be the downward drag force on the pile? Assume ' = 0.5fill. 12.30 Figure 12.49a shows a pile. Let L = 15 m, D (pile diameter) 305 mm, Hf = 3 m, fill = 17.5 kN/m3, and fill = 25°. Determine the total downward drag force on the pile. Assume that the fill is located above the water table and that = 0.5fill.arrow_forwardA square prestressed concrete pile with a cross section 0.3 m by 0.3 m is driven 15 m into overconsolidated clays with properties as defined: From the ground surface to a depth of 7 m, the unit weight is 17 kN/m3 and the shear strength cohesion cu is 70 kPa; below 7 m, the soil unit weight is 18.5 kN/m3 and cohesion is 105 kPa. Use the total stress α-method to calculate both the design downward axial capacity and upward axial capacity, using a factor of safety of 3 (downward and upward).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals of Geotechnical Engineering (MindTap...Civil EngineeringISBN:9781305635180Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage LearningPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage LearningPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781305081550Author:Braja M. DasPublisher:Cengage Learning
Fundamentals of Geotechnical Engineering (MindTap...
Civil Engineering
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781305081550
Author:Braja M. Das
Publisher:Cengage Learning
How to build angle braces; Author: Country Living With The Harnish's;https://www.youtube.com/watch?v=3cKselS6rxY;License: Standard Youtube License