Chapter 19, Problem 1CQ

A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the total completion time for the project?

  1. a. 3 days, because this is the minimum time
  2. b. 7 days, because this is the maximum time
  3. c. 20 days, because this is the sum of the times
  4. d. It is not possible to determine the total completion time from the given information.
Expert Solution & Answer
Check Mark
Summary Introduction

To determine: The total completion time for the project.

Answer to Problem 1CQ

D. It is not possible to determine the total completion time from the given information.

Explanation of Solution

Given information:

Four activities of a project take 4, 3, 6 and 7 days respectively.

The given scenario lacks basic information to find the completion time of the project. Details like precedence relationship is not given which makes it impossible to find the sequence of activities in which the project must be done.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Which of the following statements is correct with respect to slack time?a. The slack time of an activity is the latest completion time of the activity minus theearliest completion time.b. The slack time of an activity is the latest start time of the activity minus the earliest start time.c. The slack time of an activity determines how long an activity can be delayed withoutimpacting the overall completion of the project.d. All of these statements are correct.
When crashing a project, the general guideline is to concentrate on the path with?a. The least expensive gradientb. The most expensive gradientc. The task with the most slackd. The task with the least slack
According to the 66178 standard, it is vital that improvement projects   a. incude external advisors in order to give the broadcast possible view of the project b. seek to introduce the timescales in order to optimize the time variable c. involve all members of the organization who have any links to the process

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY