Using Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine Budgeted Cost
Refer to the information for Speedy Pete’s on the previous page. Coefficients shown by a regression program for Speedy Pete’s data are:
Required:
Use the results of regression to make the following calculations:
- 1. Calculate the fixed cost of deliveries and the variable rate per delivery.
- 2. Construct the cost formula for total delivery cost.
- 3. Calculate the budgeted cost for next month, assuming that 3,000 deliveries are budgeted. (Note: Round answers to the nearest dollar.)
Use the following information for Brief Exercises 3-26 through 3-29:
Speedy Pete’s is a small start-up company that delivers high-end coffee drinks to large metropolitan office buildings via a cutting-edge motorized coffee cart to compete with other premium coffee shops. Data for the past 8 months were collected as follows:
Trending nowThis is a popular solution!
Chapter 3 Solutions
Managerial Accounting: The Cornerstone of Business Decision-Making
- Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Refer to the information for Speedy Petes above. Speedy Petes controller wants to calculate the fixed and variable costs associated with its cutting-edge delivery service. Required: Using the high-low method, calculate the fixed cost of deliveries, calculate the variable rate per delivery, and construct the cost formula for total delivery cost. Use the following information for Brief Exercises 3-26 through 3-29: Speedy Petes is a small start-up company that delivers high-end coffee drinks to large metropolitan office buildings via a cutting-edge motorized coffee cart to compete with other premium coffee shops. Data for the past 8 months were collected as follows:arrow_forwardUsing Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine Budgeted Cost Refer to the information for Pizza Vesuvio on the previous page. Coefficients shown by a regression program for Pizza Vesuvios data are: Required: Use the results of regression to make the following calculations: 1. Calculate the fixed cost of labor and the variable rate per employee hour. 2. Construct the cost formula for total labor cost. 3. Calculate the budgeted cost for next month, assuming that 675 employee hours are budgeted. (Note: Round answers to the nearest dollar.) Use the following information for Brief Exercises 3-17 through 3-20: Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected:arrow_forwardContinuous improvement is the governing principle of a lean accounting system. Following are several performance measures. Some of these measures would be associated with a traditional standard-costing accounting system, and some would be associated with a lean accounting system. a. Materials price variances b. Cycle time c. Comparison of actual product costs with target costs d. Materials quantity or efficiency variances e. Comparison of actual product costs over time (trend reports) f. Comparison of actual overhead costs, item by item, with the corresponding budgeted costs g. Comparison of product costs with competitors product costs h. Percentage of on-time deliveries i. First-time through j. Reports of value- and non-value-added costs k. Labor efficiency variances l. Days of inventory m. Downtime n. Manufacturing cycle efficiency (MCE) o. Unused (available) capacity variance p. Labor rate variance q. Using a sister plants best practices as a performance standard Required: 1. Classify each measure as lean or traditional (standard costing). If traditional, discuss the measures limitations for a lean environment. If it is a lean measure, describe how the measure supports the objectives of lean manufacturing. 2. Classify the measures into operational (nonfinancial) and financial categories. Explain why operational measures are better for control at the shop level (production floor) than financial measures. Should any financial measures be used at the operational level? 3. Suggest some additional measures that you would like to see added to the list that would be supportive of lean objectives.arrow_forward
- Using the data in E4-2 and spreadsheet software, determine: The variable cost per unit, the total fixed cost, and R2. The plotted data points using the graphing function. Compare the results to your solutions in E4-2 and E4-3 and explain the reasons for the results.arrow_forwardData for Torleson Company are as follows: Required: 1. Calculate the sales price variance. 2. Calculate the sales volume variance. 3. Suppose that the product is in the introductory stage of the product life cycle. What information do these two variances provide to Torlesons managers?arrow_forwardThe management of Hartman Company is trying to determine the amount of each of two products to produce over the coming planning period. The following information concerns labor availability, labor utilization, and product profitability: a. Develop a linear programming model of the Hartman Company problem. Solve the model to determine the optimal production quantities of products 1 and 2. b. In computing the profit contribution per unit, management does not deduct labor costs because they are considered fixed for the upcoming planning period. However, suppose that overtime can be scheduled in some of the departments. Which departments would you recommend scheduling for overtime? How much would you be willing to pay per hour of overtime in each department? c. Suppose that 10, 6, and 8 hours of overtime may be scheduled in departments A, B, and C, respectively. The cost per hour of overtime is 18 in department A, 22.50 in department B, and 12 in department C. Formulate a linear programming model that can be used to determine the optimal production quantities if overtime is made available. What are the optimal production quantities, and what is the revised total contribution to profit? How much overtime do you recommend using in each department? What is the increase in the total contribution to profit if overtime is used?arrow_forward
- 1.The relevant costing involves making decision to the following, except: Select one: a. overcome limited factors. b. price higher or lower. c. accept or reject a special order. d. keep or drop a segment or product line. 2.Below are the methods to compute the break-even point, except: Select one: a. contribution margin method. b. cost-volume-profit graphic presentation. c. mathematical equation method. d. profit margin method. 3.The financial budget comprises of the following, except: Select one: a. cash budget. b. investment budget. c. budgeted cash flows. d. capital budget.arrow_forwardCan you provide samples/examples of tasks for developing the costing and profitability model for a new product? Should include the following: o A table showing the list of the parameters used in your model o A breakdown of the expected production costs and profitability o Calculation of the NPV of expected sales/ profitability o A sensitivity analysis that accounts for changes in any three (3) parameters of your model. o At least two trade-off rules you developed for your product developmentarrow_forwardThe performance evaluation of a cost center is typically based on its a. sales volume variance. b. ROI. c. static budget variance. d. flexible budget variance.arrow_forward
- Match the definition the term. Terms: Cost variance Overhead cost variance Price variance Quantity variance Standard costs Sales budget Production Budget Balanced scorecard Profit center Cost center Definitions: 1. A plan showing the units of goods to be sold and sales to be derived; usually starting pointing the budgeting process. 2. A system of performance measures, including the nonfinancial measures, used to asses manager performance. 3. A department that incurs cost and genrate revenues, such as a selling department 4. The difference between actual and budgeted sales or cost caused by the difference between the actual per unit and the budgeted price per unit. 5. The difference between actual cost and standard cost, made up of a price variance and a quantity variance. 6. The difference between the total overhead cost actually incurred and the total overhead cost applied to products 7. The difference between the actual budgeted cost caused by…arrow_forwardAn advantage of the flexible budget over the static budget is: Group of answer choices Flexible budget can be prepared based on the sales volume of the previous period. Flexible budget provides better comparison as it can be prepared based on the actual level of sales volume. Preparation of flexible budget is relatively less time consuming. Flexible budget requires less data.arrow_forwardPerformance reports for cost centers compare actual controllable costs with flexible budget data. total costs with static budget data. total costs with flexible budget data. controllable costs with static budget data.arrow_forward
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningEssentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage Learning
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage Learning