PRODUCTION SCHEDULING A company manufactures two products, A and B, on two machines, I and II. It has been determined that the company will realize a profit of $3/unit on Product A and a profit of $4/unit on Product B. To manufacture 1 unit of Product A requires 6 min on Machine I and 5 min on Machine II. To manufacture 1 unit of Product B requires 9 min on Machine I and 4 min on Machine II. There are 5 hr of machine time available on Machine I and 3 hr of machine time available on Machine II in each work shift. How many units of each product should be produced in each shift to maximize the company's profit? What is the largest profit the company can realize? Is there any time left unused on the machines?
PRODUCTION SCHEDULING A company manufactures two products, A and B, on two machines, I and II. It has been determined that the company will realize a profit of $3/unit on Product A and a profit of $4/unit on Product B. To manufacture 1 unit of Product A requires 6 min on Machine I and 5 min on Machine II. To manufacture 1 unit of Product B requires 9 min on Machine I and 4 min on Machine II. There are 5 hr of machine time available on Machine I and 3 hr of machine time available on Machine II in each work shift. How many units of each product should be produced in each shift to maximize the company's profit? What is the largest profit the company can realize? Is there any time left unused on the machines?
Solution Summary: The mathematical formulation of the problem leads to the following standard linear programming problem: Maximize the company's profit.
PRODUCTION SCHEDULING A company manufactures two products, A and B, on two machines, I and II. It has been determined that the company will realize a profit of $3/unit on Product A and a profit of $4/unit on Product B. To manufacture 1 unit of Product A requires 6 min on Machine I and 5 min on Machine II. To manufacture 1 unit of Product B requires 9 min on Machine I and 4 min on Machine II. There are 5 hr of machine time available on Machine I and 3 hr of machine time available on Machine II in each work shift. How many units of each product should be produced in each shift to maximize the company's profit? What is the largest profit the company can realize? Is there any time left unused on the machines?
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, subject and related others by exploring similar questions and additional content below.
Solve ANY Optimization Problem in 5 Steps w/ Examples. What are they and How do you solve them?; Author: Ace Tutors;https://www.youtube.com/watch?v=BfOSKc_sncg;License: Standard YouTube License, CC-BY
Types of solution in LPP|Basic|Multiple solution|Unbounded|Infeasible|GTU|Special case of LP problem; Author: Mechanical Engineering Management;https://www.youtube.com/watch?v=F-D2WICq8Sk;License: Standard YouTube License, CC-BY