Principles of Geotechnical Engineering (MindTap Course List)
9th Edition
ISBN: 9781305970939
Author: Braja M. Das, Khaled Sobhan
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8, Problem 8.6P
To determine
Draw the flow net for the weir and calculate the seepage under the weir.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
An earth dam is shown in Figure, Determine the seepage rate, q, in m3/day/m length.
Given: α1 =α2 =45o , L1=15m ,H=30m, H1=40m, K=4.2 ×10-4m/min
An earth dam is shown in the figure below. Determine the seepage rate. Given: a1=48 degrees, a2= 30 degrees, L1=6m, H 17m, H1=21m and k=0.007 cm/s. Use L.Casagrande Method
Show complete solution(need ASAP): The coefficient of permeability below a dam is 4 m/day. The water on the upstream side is 20 m. higher than on the downstream side. To estimate the seepage below the dam, a flow net was graphically drawn. The base of the dam is founded 1 meter below the ground. Between the heel and the toe of the dam, a distance of 30 m, there are 8 potential drops. a. Evaluate the seepage flow per meter length of the dam in cu.m per day. b. Compute the uplift force per unit length along the axis of the dam in kN/m. c. Determine the position of the uplift force from the toe of the dam in m.
Chapter 8 Solutions
Principles of Geotechnical Engineering (MindTap Course List)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- In a rectangular channel, the depths of flow before and after the hydraulic jump are respectively 0.2 m and 1.2 m. What is the energy loss in the jump?arrow_forward.An earth dam is shown in Fig 4 . Determine the seepage rate, q, in m3/day/m length. Given: α1 =350, α2 = 400, L1 = 5 m, H =7 m, H1 =10 m, and k =3 x 10 -4 cm/sec. Use Schaffernak’s solution.arrow_forwardQ1: (a) Define and explain uniform flow. How is open channel flow different from pipe flow? (b) Under what conditions the bed slope, water surface slope and the energy line slope are equal?arrow_forward
- A primary clarifier for a municipal wastewater treatment plant is to be designed for an average flow of 7570 m3/d. the regulatory agency criteria for primary clarifiers are as follows: peak overflow rate = 89.6 m3/m2.d, average overflow rate = 36.7 m3/m2d, minimum side water depth = 3 m, and peak weir loading rate = 389 m3/m.d. The ratio of peak flow to average flow = 2.75. Determine: Diameter of the sedimentation basin The length of the peripheral weir. Assume that the weir launder has a width of 50 cm (from the tank side), and the weirs are installed on one side of the launder.arrow_forwardAn earth dam is shown in the figure below Determine the seepage rate, q, in m^3/day/m length. Given: α1=35°, α2=40°, L1=5 m, H=7 m, H1=10 m, and k= 3x10^4 cm/sec.arrow_forwardDesign a circular sedimentation tank to treat 2500 m3 of raw water per day. The retention period assumed to be 2.8 hours. The process is coagulated sedimentation, assume the flow depth=2.8 m.arrow_forward
- Water depths in the upstream and on the crest of a hump were measured and they were 1.65 m and 0.435 m. Assuming that the choking effect already occurred on the hump and energy losses are negligible, what is the specific discharge and hump height in the channel? ( Show calculations and sketch) a) 0.9 m2/s and 1 m b) 1 m2/s and 0.9 m c) 1.2 m2/s and 1 m d) 1 m2/s and 1.2 marrow_forwardThe infiltration capacity of a catchment is represented by Horton’s equation as f= 0.5+ 1.2e^-0.5t where f is in cm/hr and t is in hours. Assuming the infiltration to take place at capacity rates in a storm of 4 hours duration, estimate the average rate of infiltration for the duration of the storm.arrow_forwardCompute the hydraulic radius and hydraulic depthj for a 36 inch diameter culvert with a depth of flow of 20 inchesarrow_forward
- What is the ultimate BOD 24 km downstream from the outfall? > Answer: 3.89 g/m3 What is the DO deficit 24 km downstream of the effluent discharge? > Answer: 3.192 g/m3 Question: Is it possible to reduce the BOD of the effluent to maintain the DO above 7.0 mg/L at all downstream locations along the river? If so, what is the target BOD of the effluent?arrow_forwardA periodic and spectacular water release, in China’s Henanprovince, flows through a giant sluice gate. Assume thatthe gate is 23 m wide, and its opening is 8 m high. Thewater depth far upstream is 32 m. Assuming free discharge,estimate the volume flow rate through the gate.arrow_forwardFor the rectangular channel below, what is the flow depth right before the hydraulic jump (the smallest flow depth shown in the figure)? Flow depth upstream of the spillway is 9.6 m and discharge per width of the channel is 1.1 m2/s. Assume negligible energy loss over the spillway.Choose one: 0.08 m 9.6 m 6.24 m 0.02 marrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Geotechnical Engineering (MindTap C...Civil EngineeringISBN:9781305970939Author:Braja M. Das, Khaled SobhanPublisher:Cengage LearningFundamentals of Geotechnical Engineering (MindTap...Civil EngineeringISBN:9781305635180Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
Principles of Geotechnical Engineering (MindTap C...
Civil Engineering
ISBN:9781305970939
Author:Braja M. Das, Khaled Sobhan
Publisher:Cengage Learning
Fundamentals of Geotechnical Engineering (MindTap...
Civil Engineering
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning