Illinois Furniture, Inc., produces all types of office furniture. The “Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks:
a) Draw a precedence diagram of this operation.
b) What is the cycle time for this operation?
c) What is the theoretical minimum number of workstations?
d) Assign tasks to workstations.
e) What is the idle time per cycle?
f) How much total idle time is present in an 8-hour shift?
g) What is the efficiency of the assembly line, given your answer in (d)?
a)
To draw: The precedence diagram.
Answer to Problem 13P
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Precedence diagram:
b)
To determine: The cycle time.
Introduction:
Cycle time:
Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.
Answer to Problem 13P
The cycle time is 9.6 minutes / unit.
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Formula to calculate cycle time:
Calculation of cycle time:
The cycle time is 9.6 minutes / unit.
c)
To determine: The theoretical minimum number of workstations.
Answer to Problem 13P
The theoretical minimum number of workstations is 6 workstations.
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Formula to calculate theoretical minimum number of workstations:
Calculation of theoretical minimum number of workstations:
The theoretical minimum number of workstations is 6 workstations.
d)
To assign: The different tasks to different workstations.
Explanation of Solution
Assignment of different tasks to different workstations:
Task A is assigned to station 1. Task B is assigned to station 2. Task C is assigned to station 3. Task D is assigned to station 4. Task E is assigned to station 5. Task G is assigned to station 6. Task F is assigned to station 7. Task H is assigned to station 8.
e)
To determine: The idle time per cycle.
Answer to Problem 13P
The idle time is 15 minutes / cycle.
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Calculation of idle time per cycle:
The idle time is 15 minutes / cycle.
f)
To determine: The total idle time present in an 8 hour shift.
Answer to Problem 13P
The total idle time present in an 8 hour shift is 15 hours.
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Calculation of total idle time present in an 8 hour shift:
There are 480 minutes available in a day. The longest operation time is 8 minutes. Therefore the number of cycles in a day is given by:
The total idle time is calculated by multiplying the number of cycles with the total idle time per cycle.
The total idle time present in an 8 hour shift is 15 hours.
g)
To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
Answer to Problem 13P
The efficiency is 76.6%.
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Formula to calculate efficiency:
Calculation of efficiency:
The efficiency is 76.6%
Want to see more full solutions like this?
Chapter 9 Solutions
Principles Of Operations Management
- Required: Draw a precedence diagram. Compute for the cycle time, theoretical minimum, idle time, efficiency, and balance delay. *2,000 units desired output rate *50 hrs per week of operating hours. Green Grass, Inc., a manufacturer of lawn and garden equipment, is designing an assembly line to produce a new fertilizer spreader, the Big Broadcaster. Below are the given work elements, time and immediate predecessor data.arrow_forwardAn assembly plant for the Blood Pressure RX, a portable blood pressure device, has 400 minutes available daily in the plant for the device, and the average demand is 80 units per day. Final assembly requires 6 separate tasks. Information concerning these tasks is given in the following table. Task Performance Time (minutes) Task Must Follow Task Listed Below A 4 - B 1 - C 1 A, B D 3 C E 4 D F 2 E b) Given the demand, what is the cycle time for this operation? The cycle time for this operation is enter your response here minutes/unit (enter your response as a whole number). c) What is the theoretical minimum number of workstations? The theoretical minimum number of workstations is enter your response here stations (enter your response as a whole number and, if your unrounded answer includes decimal values,…arrow_forwardSmart Kids Wonderland has decided to manufacture a new train toy set. The production process consists of which is broken into seven steps. If the company have an eight hours operating time per day with a desired output of 1450 units per day as display in Table 1. Determine the following: (Hint: Provides your answers in two decimal points) Table 1 Task Time (seconds) Predecessors A 15 - B 18 A C 14 A D 12 B E 11 C F 20 D, E G 16 F (a) Draw the network diagram to connect each workstation. (b) Determine the cycle time and the minimum number of stations needed to achieve the desired production output. (c) The assembly line efficiency rate and how many work stations are actually needed in this production process? Comment on your answer.arrow_forward
- Given the following task, times, and sequence, develop a balanced line capable of operating with a I 0-minute cycle time at Dave Visser's company. a) Draw the precedence diagram.b) Assign tasks to the minimum feasible number of workstations according to the greatest time remaining (ranked positional weight) decision rule.c) What is the efficiency of the process?arrow_forwardUse excel to show formulas 1. A company is designing a product layout for a new product. They plan to use this production line 16 hours a day in order to meet forecasted demand of 1200 units per day. For output to equal forecasted demand, what should be the actual cycle time for this production?arrow_forwardRock View Restaurant is a new fast food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:Tasks Description Task Time(InSeconds)PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served.…arrow_forward
- Rock View Restaurant is a new fast food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:Tasks Description Task Time(InSeconds)PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served.…arrow_forwardThe Action Toy Company has decided to manufacturea new train set, the production of which is broken intosix steps. The demand for the train is 4,800 units per 40-hourworkweek: a) Draw a precedence diagram of this operation.b) Given the demand, what is the cycle time for this operation?c) What is the theoretical minimum number of workstations?d) Assign tasks to workstations.e) How much total idle time is present each cycle?f) What is the efficiency of the assembly line with five stations?With six stations?arrow_forwardExplain which are the present four principles of bottleneck management?arrow_forward
- Explain why doubling the capacity of a bottleneck may not double the system capacity? Use a diagram to explain the concept of Throughput time and Bottleneck.arrow_forwardSuppose Benihana increases its restaurant seating capacity by 10% and also decreases the length of stay for each customer by 20%. As a percentage, how many more customers can it serve per hour with these changes? Please provide all necessary steps too. Thanksarrow_forwardThe Pullman Mfg., Inc., three-station work cell illus-trated in Figure S7.8 has two machines at station 1 in parallel. (The product needs to go through only one of the two machinesbefore proceeding to station 2.) The manager, Ms. Hartley, hasasked you to evaluate the system if she adds a parallel machine atstation 2.a) What is the throughput time of the new work cell?b) What is the bottleneck time of the new work cell?c) If the firm operates 8 hours per day, 6 days per week, what isthe weekly capacity of this work cell?d) How did the addition of the second machine at workstation 2affect the performance of the work cellarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.