Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC, and EAC for the project. 

 

Activity
a
b
с
d
e
Predecessor
a
с
b&c
Duration
(weeks)
2
3
3
4
5
Budget
$
300
200
250
650
420
Actual Cost
$
400
180
315
300
280
%
Complete
100
100
100
50
20
Transcribed Image Text:Activity a b с d e Predecessor a с b&c Duration (weeks) 2 3 3 4 5 Budget $ 300 200 250 650 420 Actual Cost $ 400 180 315 300 280 % Complete 100 100 100 50 20
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Quickbooks Online Accounting
Quickbooks Online Accounting
Accounting
ISBN:
9780357391693
Author:
Owen
Publisher:
Cengage