Kapoor Catering Co. uses a job cost system. Its activities in November 2020, the first month of operation, were as follows: Information State University On-the-Go Home Precious Pre-school Direct Materials Cost (food) $53,000 $36,900 $81,800 Direct Labor Cost $44,600 $40,700 $53,600 Labor Hours 2,920 3,510 4,160 The company applies overhead at a rate of $16.00 per labor hour. It completed all of its jobs in November. Total revenue for the three jobs amounted to $392,700. The actual overhead for the month was $147,400, of which $122,000 should be credited to accounts payable and $38,000 should be credited to Accumulated Depreciation. Determine the costs that should be assigned to each of the jobs.
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Kapoor Catering Co. uses a
Information | State University | On-the-Go Home | Precious Pre-school |
---|---|---|---|
Direct Materials Cost (food) | $53,000 | $36,900 | $81,800 |
Direct Labor Cost | $44,600 | $40,700 | $53,600 |
Labor Hours | 2,920 | 3,510 | 4,160 |
The company applies
Determine the costs that should be assigned to each of the jobs.
Step by step
Solved in 4 steps