Mean Raw Processing Time Number of Parallel Machines Installed Capacity (jobs per Bottleneck? (Yes day) Station or No) 5 hours #2 15+0.5-2 hours 83 183 hours What is the whole factory's capacity (aka bottleneck rate) in jobs per day? O 144 jobs per day 12 jobs per day O 1311 jobs per day O 48 jobs per day Number of Capacity (jobs per Bottleneck? (Yes day) Mean Raw Processing Station Parallel Machines Time or Noj Installed #1 5 hours 4. 12 15+0.5 - 2 hours #3 1.83 hours demand rate is 9.6 jobs per day, what is the capacity utilization at the bottleneck? O 3ax O SON O 100%

ECON MICRO
5th Edition
ISBN:9781337000536
Author:William A. McEachern
Publisher:William A. McEachern
Chapter7: Production And Cost In The Firm
Section: Chapter Questions
Problem 3.7P
icon
Related questions
Question
Number of
Mean Raw Processing
Capacity (Jobs per Bottleneck? (Yes
day)
Station
Parallel Machines
Time
or No)
Installed
#1
5 hours
#2
15+0.5- 2 hours
#3
183 hours
What is the whole factory's capacity (aka. bottleneck rate) in "jobs per day?
O 144 jobs per day
12 jobs per day
O 13.11 jobs per day
O 48 jobs per day
Number of
Parallel Machines
Installed
Capacity (Jobs per Bottleneck? (Yes:
day)
Mean Raw Processing
Station
Time
or No)
#1
5 hours
4.
#2
1.5+0.5-2 hours
2
#3
1.83 hours
f demand rate is 9.6 jobs per day, what is the capacity utilization at the bottleneck?
O 38%
O SON
O 100%
O 40%
Transcribed Image Text:Number of Mean Raw Processing Capacity (Jobs per Bottleneck? (Yes day) Station Parallel Machines Time or No) Installed #1 5 hours #2 15+0.5- 2 hours #3 183 hours What is the whole factory's capacity (aka. bottleneck rate) in "jobs per day? O 144 jobs per day 12 jobs per day O 13.11 jobs per day O 48 jobs per day Number of Parallel Machines Installed Capacity (Jobs per Bottleneck? (Yes: day) Mean Raw Processing Station Time or No) #1 5 hours 4. #2 1.5+0.5-2 hours 2 #3 1.83 hours f demand rate is 9.6 jobs per day, what is the capacity utilization at the bottleneck? O 38% O SON O 100% O 40%
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Cobb-Douglas Production Function
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
ECON MICRO
ECON MICRO
Economics
ISBN:
9781337000536
Author:
William A. McEachern
Publisher:
Cengage Learning
Exploring Economics
Exploring Economics
Economics
ISBN:
9781544336329
Author:
Robert L. Sexton
Publisher:
SAGE Publications, Inc
Principles of Microeconomics
Principles of Microeconomics
Economics
ISBN:
9781305156050
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Essentials of Economics (MindTap Course List)
Essentials of Economics (MindTap Course List)
Economics
ISBN:
9781337091992
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Microeconomic Theory
Microeconomic Theory
Economics
ISBN:
9781337517942
Author:
NICHOLSON
Publisher:
Cengage
Principles of Economics 2e
Principles of Economics 2e
Economics
ISBN:
9781947172364
Author:
Steven A. Greenlaw; David Shapiro
Publisher:
OpenStax