Please help with correct answers in details: Step by step The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources, Landon's management learned that a competitor is working to introduce a similar product. As a result, Landon's top management increased its pressure on the product development group. The group's leader turned to PERT/CPM as an aid to scheduling the activities remaining before the new product can be brought to the market.   The activity time estimates (in weeks) are listed in the following table. Activity Optimistic Most Probable Pessimistic A 3 4 5 B 3 3.5 7 C 4 5 6 D 2 3 4 E 5 8 11 F 8.5 9.5 13.5 G 4.5 6 7.5 H 6 7 14 I 2 2.5 6 J 4 5 6   a) Develop an activity schedule for this project and identify the critical path activities. (Enter your answers as a comma-separated list.) b) Based solely on the critical path, what is the probability that the project will be completed so that Landon Corporation may introduce the new product within 23 weeks? (Round your answer to four decimal places.) (c) Based solely on the critical path, what is the probability that the project will be completed so that Landon Corporation may introduce the new product within 29 weeks? (Round your answer to four decimal places.)

Principles of Management
OER 2019th Edition
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax
Chapter17: Organizational Planning And Controlling
Section: Chapter Questions
Problem 1CTQ: What do you think are some of the difficulties of adding 25 percent more employees for the holiday...
icon
Related questions
Question

Please help with correct answers in details: Step by step

The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources, Landon's management learned that a competitor is working to introduce a similar product. As a result, Landon's top management increased its pressure on the product development group. The group's leader turned to PERT/CPM as an aid to scheduling the activities remaining before the new product can be brought to the market.
 
The activity time estimates (in weeks) are listed in the following table.
Activity Optimistic Most Probable Pessimistic
A 3 4 5
B 3 3.5 7
C 4 5 6
D 2 3 4
E 5 8 11
F 8.5 9.5 13.5
G 4.5 6 7.5
H 6 7 14
I 2 2.5 6
J 4 5 6
 
a) Develop an activity schedule for this project and identify the critical path activities. (Enter your answers as a comma-separated list.)
b) Based solely on the critical path, what is the probability that the project will be completed so that Landon Corporation may introduce the new product within 23 weeks? (Round your answer to four decimal places.)
(c) Based solely on the critical path, what is the probability that the project will be completed so that Landon Corporation may introduce the new product within 29 weeks? (Round your answer to four decimal places.)
 
 
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 1 steps

Blurred answer
Knowledge Booster
Business reports
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College