The durations and direct costs for each activity under both normal and crash conditions are given in the following table. Establish the schedule and the least cost for expediting the contract. Determine the optimum cost of the contract assuming the indirect cost is 125 $/day. 1 2 3 4 5 6 7 8 9 ID Predecessor(s) 1 1 2 2 3 3,5 6 4,7,8 Normal Duration (days) 12 8 15 23 5 5 20 13 12 Cost (S) 7000 5000 4000 5000 1000 3000 6000 2500 3000 Crash Duration (days) 10 6 12 23 4 4 15 11 10 Cost (S) 7200 5300 4600 5000 1050 3300 6300 2580 3150

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.2SB
icon
Related questions
Question

Please don't answer in image format and it should be in step by step format and provide fast solution

The durations and direct costs for each activity under both normal and crash conditions are given in the following table. Establish
the schedule and the least cost for expediting the contract. Determine the optimum cost of the contract assuming the indirect cost
is 125 $/day.
1
2
3
4
5
6
7
8
9
ID
Predecessor(s)
1
1
2
2
3
3,5
6
4,7,8
Normal
Duration (days)
12
8
15
23
5
5
20
13
12
Cost ($)
7000
5000
4000
5000
1000
3000
6000
2500
3000
Crash
Duration (days)
10
6
12
23
4
4
15
11
10
Cost ($)
7200
5300
4600
5000
1050
3300
6300
2580
3150
Transcribed Image Text:The durations and direct costs for each activity under both normal and crash conditions are given in the following table. Establish the schedule and the least cost for expediting the contract. Determine the optimum cost of the contract assuming the indirect cost is 125 $/day. 1 2 3 4 5 6 7 8 9 ID Predecessor(s) 1 1 2 2 3 3,5 6 4,7,8 Normal Duration (days) 12 8 15 23 5 5 20 13 12 Cost ($) 7000 5000 4000 5000 1000 3000 6000 2500 3000 Crash Duration (days) 10 6 12 23 4 4 15 11 10 Cost ($) 7200 5300 4600 5000 1050 3300 6300 2580 3150
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 7 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning