Typed solution The product design group of Iyengar Electric​ Supplies, Inc., has determined that it needs to design a new series of switches. It must decide on one of three design strategies. The market forecast is for 200,000 units. The better and more sophisticated the design strategy and the more time spent on value​ engineering, the less will be the variable cost. The chief of engineering​ design, Dr. W. L.​ Berry, has decided that the following costs are a good estimate of the initial and variable costs connected with each of the three strategies explained below. ​Low-tech​: a​ low-technology, low-cost process consisting of hiring several new junior engineers. This option has a fixed cost of ​$40,000 and​ variable-cost probabilities of 0.5 for ​$0.56​, 0.1 for ​$0.47​,and 0.4 for​ $0.41. Subcontract​: a​ medium-cost approach using a good outside design staff. This approach would have a fixed cost of ​$75,000 and​ variable-cost probabilities of 0.7 of ​$0.49​, 0.2 of ​$0.46​, and 0.1 of ​$0.33. ​High-tech​: a​ high-technology approach using the very best of the inside staff and the latest​ computer-aided design technology. This approach has a fixed cost of ​$80,000 and​ variable-cost probabilities of 0.7 of ​$0.38 and 0.3 of ​$0.35. What is the best decision based on an expected monetary value​ (EMV) criterion? (Note​:We want the lowest​ EMV, as we are dealing with costs in this​ problem.) A) High-tech B)Low-tech C)Subcontract

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Typed solution

The product design group of Iyengar Electric​ Supplies, Inc., has determined that it needs to design a new series of switches. It must decide on one of three design strategies. The market forecast is for

200,000

units. The better and more sophisticated the design strategy and the more time spent on value​ engineering, the less will be the variable cost. The chief of engineering​ design, Dr. W. L.​ Berry, has decided that the following costs are a good estimate of the initial and variable costs connected with each of the three strategies explained below.

​Low-tech​:

a​ low-technology, low-cost process consisting of hiring several new junior engineers. This option has a fixed cost of

​$40,000 and​ variable-cost probabilities of 0.5 for ​$0.56​, 0.1 for ​$0.47​,and 0.4 for​ $0.41.

Subcontract​: a​ medium-cost approach using a good outside design staff. This approach would have a fixed cost of

​$75,000 and​ variable-cost probabilities of 0.7 of ​$0.49​, 0.2 of ​$0.46​, and 0.1 of ​$0.33.

​High-tech​: a​ high-technology approach using the very best of the inside staff and the latest​ computer-aided design technology. This approach has a fixed cost of ​$80,000 and​ variable-cost probabilities of 0.7 of ​$0.38 and 0.3 of ​$0.35.

What is the best decision based on an expected monetary value​ (EMV) criterion? (Note​:We want the lowest​ EMV, as we are dealing with costs in this​ problem.)

A) High-tech

B)Low-tech

C)Subcontract

 

 
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Forecasting methods
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.