Principles of Management
Principles of Management
OER 2019 Edition Edition
ISBN: 9780998625768
Author: OpenStax
Publisher: OpenStax College
Bartleby Related Questions Icon

Related questions

Question
You may need to use the appropriate technology to answer this question.
Mueller
Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 46-week completion date requested by the owner. The Mueller project manager prepared the following project network.
B
H
Start
A
C
G
Finish
E
Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows.
Activity Optimistic Most Probable
Pessimistic
A
4
12
B
6
7
8
C
6
18
D
3
5
7
E
6
9
18
F
5
8
17
G
10
15
20
H
5
13
(a) Find the critical path. (Enter your answers as a comma-separated list.)
(b) What is the expected project completion time (in weeks)?
weeks
i
(c) Based only on the critical path, what is the estimated probability the project can be completed in 46 weeks as requested by the owner? (Round your answer to four decimal places.)
(d) Based only on the critical path, what is the estimated probability the building project could run more than months late? Use 59 weeks for this calculation. (Round your answer to four decimal places.)
(e) What should the construction company tell the owner? (Enter your free-form answer using as many characters as necessary.)
expand button
Transcribed Image Text:You may need to use the appropriate technology to answer this question. Mueller Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 46-week completion date requested by the owner. The Mueller project manager prepared the following project network. B H Start A C G Finish E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. Activity Optimistic Most Probable Pessimistic A 4 12 B 6 7 8 C 6 18 D 3 5 7 E 6 9 18 F 5 8 17 G 10 15 20 H 5 13 (a) Find the critical path. (Enter your answers as a comma-separated list.) (b) What is the expected project completion time (in weeks)? weeks i (c) Based only on the critical path, what is the estimated probability the project can be completed in 46 weeks as requested by the owner? (Round your answer to four decimal places.) (d) Based only on the critical path, what is the estimated probability the building project could run more than months late? Use 59 weeks for this calculation. (Round your answer to four decimal places.) (e) What should the construction company tell the owner? (Enter your free-form answer using as many characters as necessary.)
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Similar questions
Recommended textbooks for you
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub