preview

Toshiba Production Case

Good Essays

Designing Toshiba’s Notebook Computer Line
A Study of Manufacturing Capacity

12/12/2011
MGT 393-03

Introduction
We analyzed a Toshiba assembly line plan for a new subnotebook computer. The engineering section manager, Toshihiro Nakamura, wants to make changes to the line process as designed by the engineers. The basic assembly line equipment and space already exist within the Toshiba plant, so the subnotebook assembly process must conform to those preexisting constraints. Specifically, the assembly line is a straight 14.4-meter conveyor system that can accommodate 8 to 12 workers plus one supporter to aid in the assembly process. The employees work at assembling for 7.5 hours a day. The computers are assembled from …show more content…

Before making any major modification to the process, we assumed that individual operations could not be split from the engineers’ plans.
Other assumptions that we made for the case study were that we could only use the 7.5-hour workday and one line of production. We also assumed that we were limited to the range of 8 to 12 people stated in the problem. Because we are making complex equipment, we assumed that we could not change the order of the operations themselves but that we could have a station do varying combinations of operations. The projections in the Excel spreadsheet also assume that the engineers’ specified times would be accurate once production begins. Regarding the hardware testing operations, the activities are to be performed on three computers concurrently, so we divided the operation times by three to arrive at the true operation times.
Once we began our changes, we had to make more assumptions since we realized that we had to be able to divide the first operation into two parts, as the operation time was 100 seconds, greater than the maximum cycle time needed (90seconds) to achieve our goal of 300 computers in a shift. We also assumed that with an upgrade, we could change the hardware testing software activity time to 50% of the original time. We also assumed we could change the screwing operations to decrease the needed time by changing the action to

Get Access